v1ch6
Report of the PRESIDENTIAL COMMISSION

on the Space Shuttle Challenger Accident
Chapter VI: An Accident Rooted in

History.
Early Design
120
] The Space Shuttle's

Solid Rocket Booster problem began with the faulty design of its

joint and increased as both NASA and contractor management first

failed to recognize it as a problem, then failed to fix it and

finally treated it as an acceptable flight risk.
Morton Thiokol, Inc., the contractor, did not

accept the implication of tests early in the program that the design

had a serious and unanticipated flaw.
NASA did not accept the judgment of its engineers that

the design was unacceptable, and as the joint problems grew in number

and severity NASA minimized them in management briefings and reports.
Thiokol's stated position was that "the condition is

not desirable but is acceptable."
Neither Thiokol nor NASA expected the rubber

O-rings sealing the joints to be touched by hot gases of motor

ignition, much less to be partially burned. However, as tests and

then flights confirmed damage to the sealing rings, the reaction by

both NASA and Thiokol was to increase the amount of damage considered

"acceptable." At no time did management either recommend a redesign

of the joint or call for the Shuttle's grounding until the problem

was solved.
Thiokol was selected to receive the NASA

contract to design and build the Solid Rocket Boosters on November

20, 1973.
The booster was the largest Solid

Rocket Motor ever produced in the United States; it was also the

first solid motor program managed by NASA's Marshall Space Flight

Center in Huntsville, Alabama.
Costs were the primary concern of NASA's

selection board, particularly those incurred early in the

program.
Thiokol's three competitors were Aerojet Solid

Propulsion Co., Lockheed Propulsion Co. and United Technologies. The

Source Evaluation Board on the proposals rated Thiokol fourth under

the design, development and verification factor, second under the

manufacturing, refurbishment and product support factor and first

under the management factor.
Thiokol received the second highest overall

Mission Suitability score, tied with United

Technologies.
In a December 12, 1973, report, NASA selection

officials said Thiokol's "cost advantages were substantial and

consistent throughout all areas evaluated."
They also singled out Thiokol's joint design for

special mention.
"The Thiokol motor case joints utilized dual

O-rings and test ports between seals, enabling a simple leak check

without pressurizing the entire motor," the officials' report said.

"This innovative design feature increased reliability and decreased

operations at the launch site, indicating good attention to low cost

(design, development, testing and engineering) and production."
"We noted that the [NASA Source Selection]

board's analysis of cost factors indicated that Thiokol could do a

more economical job than any of the other proposers in both the

development and the production phases of the program; and that,

accordingly, the cost per flight to be expected from a Thiokol-built

motor would be the lowest," the officials said. "We, therefore,

concluded that any selection other than Thiokol would give rise to an

additional cost of appreciable size."
The Selection officials said they "found no

other [
121
] factors bearing upon the selection that ranked in

weight with the foregoing."
Cost consideration overrode any other-

objections, they decided. We concluded that the main criticisms of

the Thiokol proposal in the Mission Suitability evaluation were

technical in nature, were readily correctable, and the costs to

correct did not negate the sizable Thiokol cost advantage," the

selection officials concluded.
The cost-plus-award-fee contract, estimated to

be worth $800 million, was awarded to Thiokol.
The design of the Shuttle Solid Rocket Booster

was primarily based on the Air Force's Titan III solid rocket, one of

the most reliable ever produced. Thiokol hoped to reduce new design

problems, speed up the development program and cut costs by borrowing

from the Titan design. In Thiokol's Solid Rocket Motor proposal, the

rocket fuel is contained in four- forged steel cases which are

stacked one on top of the other. The casings were connected by a

circumferential tang and clevis, as were the

Titans.
10
Despite their many similarities, the Thiokol

Solid Rocket Booster and the Titan motors had some significant design

differences. For example, the joints of the Titan were designed so

that the insulation of one case fits tightly against the insulation

of the adjacent case to form a more gastight fit than the Thiokol

design. One O-ring bore seal was used in each Titan joint to stop any

hot gas pressure that might pass by the insulation overlap,
11
but in the Titan design the O-ring was able but not

intended to take the brunt of the combustion pressure. In contrast,

the Thiokol O-rings were designed to take the brunt of the combustion

pressure, with no other gas barriers present except an insulating

putty. Also, the Solid Rocket Motor joint had two O-rings, the second

to provide a backup in case the primary seal failed.
Asbestos-filled putty was used in the Solid

Rocket Motor to pack the space between the two case segments to

prevent O-ring damage from the heat of combustion gases.
12
Thiokol believed the putty was plastic, so when acted

on by the combustion pressure at the motor's ignition the putty flow

towards the O-ring would compress the air in the gap between the

putty and the primary O-ring.
13
The compressed air, in turn, would.....
Figure 1.
Comparison of Original Design to Design Used.
122
] ...cause the

primary O-ring to extrude into the gap between the clevis and the

tang, behind the primary O-ring groove, thereby sealing the opening.

If the primary O-ring did not seal, the intent was that the secondary

would pressurize and seal the joint by extruding into the gap behind

its groove.
14
Another difference in the Solid Rocket Motor

and the Titan was that the tang portion of the Thiokol joint was

longer in order to accommodate two O-rings instead of one. It was

more susceptible to bending under combustion pressure than the Titan

joint, as post-design tests and later flight experience

demonstrated.
15
The initial Thiokol design proposal was

changed before the production motors were manufactured. Originally,

the joint seal design incorporated both a face seal and a bore

seal.
16
Figure

.) However, the motor that was

eventually used had double bore O-rings. The original bore seal/face

seal design was chosen because it was anticipated that it "provides

[better] redundance over a double bore ring seal since each is

controlled by different manufacturing tolerances, and each responds

differently during joint assembly. "
17
Because the early design incorporated tolerances

similar to the Titan and it also incorporated a face seal, Thiokol

believed it possessed "complete, redundant seal capability."
18
Nevertheless, as the Solid Rocket Motor

program progressed, Thiokol-with NASA's concurrence-dropped the

face/bore seal design for one using a double bore seal (
Figure 1
). NASA engineers at Marshall said the original design

would have required tapered pins to maintain necessary tolerances and

assure enough"squeeze" on the face-sealing

O-ring.
19
However, design analysis determined that motor

ignition would create tension loads on the joint sufficient to cause

the tapered pins to pop out. Solving that would have meant designing

some type of pin-retainers. Moreover, the rocket assembly was much

easier with the dual bore seals. Because inspections and tests had to

be conducted on the Solid Rocket Motor stack, horizontal assembly was

required. Thiokol engineer, Howard McIntosh, described this in a

Commission interview on April 2, 1986:
"We were concerned very much about

the horizontal assembly that we had to do to do the static tests. The

Titan had always been assembled vertically, and so there had never

been a larger rocket motor to our knowledge that was assembled

(horizontally)".
20
Because of the extremely tight tolerances in

the joints caused by horizontal assembly, McIntosh noted, "We . . .

put the bore seals in there, and we opened the tolerance in the gaps

slightly to accommodate that."
21
To tighten the joint's fit and to increase the squeeze

in the O-rings to compensate for the larger tolerances, Thiokol

subsequently put thin metal shims between the outer walls of the tang

and clevis.
Another significant feature of the Thiokol

design was a vent, or port, on the side of the motor case used after

assembly to check the sealing of the O-rings. As will be noted later,

this leak check eventually became a significant aspect of the O-ring

erosion phenomenon.
22
The manufacture of the O-rings themselves

constituted another difference between the Titan and the Thiokol

Solid Rocket Motor. While both O-rings were Viton rubber, the Titan

O-rings were molded in one piece. The Solid Rocket Motor O-rings were

made from sections of rubber O-ring material glued together. The

specifications allowed five such joints, a number chosen arbitrarily,

and the vendor routinely made repairs of voids and inclusions after

getting the material supplies. Only surface inspections were

performed by Thiokol and by the manufacturer.
Finally, unlike the Titan, the Thiokol Solid

Rocket Motor was designed for multiple firings. To reduce program

costs, each Thiokol motor case for the Shuttle was to be recovered

after flight and reused up to 20 times.
23
Early Tests
Thiokol began testing the Solid Rocket Motor

in the mid-1970's. One of the early important tests was a 1977

"hydroburst test."
24
Its purpose was to test the strength of the

steel cases by simulating a motor firing. The case was pressurized

with water to about one and one-half times the pressure of an ignited

motor (about 1,500 pounds per square inch) to make certain the case

had adequate structural margin.
25
Also, to measure the pressure between the O-rings,

engineers attached instruments to the leak test port at a segment

joint. Although the test was successful in that it demonstrated the

case met strength requirements, test measurements showed that,

contrary to design expectations, the joint [
123
] tang and inside

clevis bent away from each other instead of toward each other and by

doing so reduced-instead of increased-pressure on the 0-ring in the

milliseconds after ignition.
26
This phenomenon was called "joint rotation."

Testifying before the Commission, Arnold Thompson, Thiokol's

supervisor of structures, said,
"We discovered that the joint was

opening rather than closing as our original analysis had indicated,

and in fact it was quite a bit. I think it was up to 52

onethousandths of an inch at that time, to the primary

O-ring."
27
Thiokol reported these initial test findings

to the NASA program office at Marshall. Thiokol engineers did not

believe the test results really proved that "joint rotation" would

cause significant problems,
28
and scheduled

no additional tests for the specific purpose of confirming or

disproving the joint gap behavior.
Design Objections
Reaction from Marshall to the early Solid

Rocket Motor test results was rapid and totally opposite of

Thiokol's. In a September 2, 1977 memorandum, Glenn Eudy, Marshall's

Chief Engineer of the Solid Rocket Motor Division, informed Alex

McCool, Director of the Structures and Propulsion Laboratory, that

the assembly of a developmental motor provided early indications that

the Thiokol design:
"Allowed O-ring clearance.... Some

people believe this design deficiency must be corrected by some

method such as shimming and perhaps design modification to the case

joint for hardware which has not been final machined.... I personally

believe that our first choice should be to correct the design in a

way that eliminates the possibility of O-ring clearance.... Since

this is a very critical SRM issue, it is requested that the

assignment results be compiled in such a manner as to permit review

at the S&E Director's level as well as project manager."
After seeing the data from the September 1977

hydroburst test, Marshall engineer Leon Ray submitted a report

entitled "Solid Rocket Motor Joint Leakage Study" dated October 21,

1977. It characterizes "no change" in the Thiokol design as

"unacceptable"-"tang can move outboard and cause excessive joint

clearance resulting in seal leakage. Eccentric tang/clevis interface

can cause O-ring extrusion when case is pressurized." Ray recommended

a "redesign of the tang and reduce tolerance on the clevis" as the

"best option for a long-term fix."
29
After Ray's 1977 report, John Q. Miller, chief

of the Solid Rocket Motor branch at Marshall, signed and sent a

memorandum on January 9, 1978 to his superior, Glenn Eudy, describing

the problems evident in the Solid Rocket Motor joint seal. "We see no

valid reason for not designing to accepted standards," the memo said,

and it emphasized that proper sealing of the joint by use of shims to

create necessary O-ring pressure was "mandatory to prevent hot gas

leaks and resulting catastrophic failure."
30
One year later, not having received a response

to his 1978 memo, Miller signed and forwarded a second memo

strenuously objecting to Thiokol's Solid Rocket Motor joint seal

design. This memo, dated January 19, 1979, opened with: "We find the

Thiokol position regarding design adequacy of the clevis joint to be

completely unacceptable...."
31
The memorandum made three principal objections to

Thiokol's joint design. The first was the "large sealing surface gap

created by extensive tang/clevis relative movement." The memo said

this movement, the so-called"joint rotation," caused the primary

O-ring to extrude into the gap, "forcing the seal to function in a

way which violates industry and government O-ring application

practices."
32
Moreover, joint rotation allowed the secondary O-ring

to "become completely disengaged from its sealing surface on the

tang." Finally, the memorandum noted that although Thiokol's contract

required all high pressure case seals to be verifiable, "the clevis

joint secondary O-ring seal has been verified by tests to be

unsatisfactory."
33
A copy of the second memorandum was sent to George

Hardy, then Solid Rocket Booster project manager at Marshall. Thiokol

apparently did not receive copies of either Miller memorandum, and no

reply from Eudy to Miller has been found.
The Commission has learned that Leon Ray

actually authored the Miller memos to Eudy, although Miller signed

them and concurred in the objections raised.
34
During February, 1979, Ray also reported on a visit he

made to two O-ring manufacturers-the Precision Rubber Products

Corporation at Lebanon Tennessee, and the Parker Seal Co. at

Lexington, Kentucky.
35
Eudy [
124
] accompanied Ray on

the Precision visit. The purpose of the trips was to give the

manufacturers the data on the O-ring experiences at Thiokol and to

"seek opinions regarding potential risks involved," Ray wrote in a

February 9, 1979, memo describing the visit. Officials at Precision

did "voice concern for the design, stating that the Solid Rocket

Motor O-ring extrusion gap was larger than that covered by their

experience," Ray reported. "Their first thought was that the O-ring

was being asked to perform beyond its intended design and that a

different type of seal should be considered," Ray

added.
36
During the Commission hearing on May 2, 1986,

Ray was asked why the 1978 and 1979 memoranda were written:
Mr. Ray
: The

reason they were written was as a result of test data that we had,

and I have to go back to, I guess, a little bit further back in time

than these memos. When the joint was first designed, the analysis

produced by Thiokol says the joint would close, the extrusion gap

would actually close.
We had quite a debate about that until we did

a test on the first couple of segments that we received from the

manufacturer, which in fact showed that the joint did open. Later on

we did some tests with the structural test article, and this is

mentioned in the memo as STA-1 [Structural Test Article].
At that time, we really nailed it down. We got

some very accurate numbers on joint rotation, and we know for a fact

that during these tests that, just what the memo says, the joint

rotated. The primary O-ring was extruded up into the joint. The

secondary O-ring did in fact detach from the

seat.
37
No records show Thiokol was informed of the

visits, and the O-ring design was not changed.
Thiokol's phase 1 certification review on

March 23, 1979, mentioned leak check failures, and forces during case

joint assembly that resulted in clevis O-ring grooves not conforming

with tang sealing surfaces. However, this was not listed as a problem

or a failure.
38
Verification and Certification

Committee
While Ray was warning of problems with joint

rotation, static motor tests in July 1978 and April 1980 again were

demonstrating that inner tang/clevis relative movement was greater

than originally predicted.
39
Thiokol continued to question the validity of these

joint rotation measurements and their effect on the availability of

the secondary O-ring.
In 1980, NASA empanelled a Space Shuttle

Verification/Certification Committee to study the flight worthiness

of the entire Shuttle system. A subdivision of that group, the

Propulsion Committee, met with NASA Solid Rocket Motor program

personnel and raised several concerns about the joint

design.
40
The Committee pointed out that the booster's leak test

pressurized the primary O-ring in the wrong direction so that the

motor ignition would have to move the ring across its groove before

it sealed. The Committee added that the effect of the insulation

putty was not certain. Redundancy of the O-rings was also listed as a

verification concern. The same report, however, said "the Committee

understands from a telecon that the primary purpose of the second

O-ring is to test the primary and that redundancy is not a

requirement." George Hardy testified that the Committee's statement

conflicted with his understanding:
"The discussion there or the

reference there to a telecon-and I don't know who that was with-that

implies there was no intent for the joint to be redundant is totally

foreign to me. I don't know where they would have gotten that

information because that was the design requirement for the joint."
41
In May 1980, the Verification/Certification

Committee recommended that NASA conduct full-scale tests to verify

the field joint integrity, including firing motors at a mean bulk

propellant temperature range of 40-90 degrees Fahrenheit. The panel

also asked NASA to:
"Perform case burst test with one

O-ring removed. During the burst test for final verification of the

motor case safety factor, one of the two O-rings failed by extrusion

and leaked. The analysis used for additional verification did not

include further gap openings caused by joint deflection at

pressurization or any deflections caused by bending loads. The panel

considers the above to be inadequate to provide operational program

reliability, and marginal to provide adequate [
125
] safety factor

confidence on [Shuttle flight] one."
42
The NASA program response to these issues was

included in the final Committee report in September 1980. It said

that the original hydroburst tests and the lightweight case tests,

being conducted at the time, satisfied the intent of the Committee's

recommendations. Moreover, the response stated: "NASA specialists

have reviewed the field joint design, updated with larger O-rings and

thicker shims and found the safety factors to be adequate for the

current design. Re-analysis of the joint with larger O-rings and

thicker shims is being accomplished as part of the lightweight case

program.... The joint has been sufficiently verified with the testing

accomplished to date (joint lab tests, structural test article, and

seven static firings and the two case configuration burst tests) and

currently scheduled for lightweight case

program."
43
Criticality Classification and

Changes
The Solid Rocket Motor certification was

deemed satisfactory by the Propulsion Committee of the

Verification/Certification Group on September 15, 1980. Shortly

thereafter, on November 24, 1980, the Solid Rocket Booster joint was

classified on the Solid Rocket Booster Critical Items List as

criticality category 1 R. NASA defines "Criticality 1R" as any

subsystem of the Shuttle that contains "redundant hardware, total

element failure of which could cause loss of life or

vehicle."
44
The use of "R", representing redundancy, meant that

NASA believed the secondary O-ring would pressurize and seal if the

primary O-ring did not. Nonetheless, the 1980 Critical Items List

(CIL) states:
"Redundancy of the secondary field

joint seal cannot be verified after motor case pressure reaches

approximately 40 percent of maximum expected operating pressure. It

is known that joint rotation occurring at this pressure level with a

resulting enlarged extrusion gap causes the secondary O-ring to lose

compression as a seal. It is not known if the secondary O-ring would

successfully reseal if the primary O-ring should fail after motor

case pressure reaches or exceeds 40 percent of maximum expected

operating pressure."
When asked about the text of the 1980

Criticality 1R classification, Arnold Aldrich, NASA Manager of the

National Space Transportation System, said,
"The way that . . . language

[reads], I would call it [criticality] 1."
45
Notwithstanding this apparent contradiction in

the classification 1R and the questionable status of the secondary

described in the text of the CIL, the joint carried a 1 R

classification from November 1980 through the flight of STS-5

(November 1982).
The Space Shuttle first flew on April 12-14,

1981. After the second flight, STS-2, in November 1981, inspection

revealed the first in-flight erosion of the primary

O-ring.
46
It occurred in the right Solid Rocket Booster's aft

field joint and was caused by hot motor gases.
47
The damage to the ring proved to be the worst ever

found on a primary O-ring in a field joint on any recovered Solid

Rocket Booster.
48
Post-flight examination found an erosion depth of .053

inches on the primary O-ring; nonetheless, the anomaly was not

reported in the Level I Flight Readiness Review for STS-3 held on

March 9, 1982. Furthermore, in 1982 the STS-2 O-ring erosion was not

reported on the Marshall problem assessment system and given a

tracking number as were other flight anomalies.
49
In mid- 1982, two significant developments

took place. Because Thiokol believed blow holes in the insulating

putty were a cause of the erosion on STS-2,
50
they began tests of the method of putty layup and the

effect of the assembly of the rocket stages on the integrity of the

putty. The manufacturer of the original putty, Fuller-O'Brien,

discontinued the product and a new putty, from the Randolph Products

Company, was tested and selected in May 1982.
51
The new Randolph putty was eventually substituted for

the old putty in the summer of 1983, for the STS-8 Solid Rocket Motor

flow.
52
A second major event regarding the joint seal

occurred in the summer of 1982. As noted before, in 1977-78, Leon Ray

had concluded that joint rotation caused the loss of the secondary

O-ring as a backup seal. Because of May 1982 high pressure O-ring

tests and tests of the new lightweight motor case, Marshall

management [
126
] finally accepted the conclusion that the secondary

O-ring was no longer functional after the joints rotated when the

Solid Rocket Motor reached 40 percent of its maximum expected

operating pressure. It obviously followed that the dual O-rings were

not a completely redundant system, so the Criticality 1R had to be

changed to Criticality 1.
53
This was done at Marshall on December 17, 1982. The

revised Critical Items List read (See pages 157 and 158):
"Criticality Category 1.
"Failure Mode and Causes: Leakage at case

assembly joints due to redundant O-ring seal failures or primary seal

and leak check port O-ring failure.
"Note. Leakage of the primary O-ring seal

is classified as a single-failure point due to possibility of loss of

sealing at the secondary O-ring because of joint rotation after motor

pressurization.
"Failure Effect Summary: Actual Loss-
Loss of mission, vehicle and crew due

to metal erosion, burn through, and probable case burst resulting in

fire and deflagration. .
"Rationale for Retention:
"The Solid Rocket Motor case joint design is

common in the lightweight and regular weight cases having identical

dimensions. The joint concept is basically the same as the single

O-ring joint successfully employed on the Titan III Solid Rocket

Motor.... On the Shuttle Solid Rocket Motor, the secondary O-ring was

designed to provide redundancy and to permit a leak check, ensuring

proper installation of the O-rings. Full redundancy exists at the

moment of initial pressurization. However, test data shows that a

phenomenon called joint rotation occurs as the pressure rises,

opening up the O-ring extrusion gap and permitting the energized ring

to protrude into the gap. This condition has been shown by test to be

well within that required for safe primary O-ring sealing. This gap

may, however, in some cases, increase sufficiently to cause the

unenergized secondary O-ring to lose compression, raising question as

to its ability to energize and seal if called upon to do so by

primary seal failure. Since, under this latter condition only the

single O-ring is sealing, a rationale for retention is provided for

the simplex mode where only one O-ring is acting" [emphasis added] .
54
The retention rationale for the "simplex" or

single O-ring seal was written on December 1, 1982, by Howard

McIntosh, a Thiokol engineer.
55
This document gave the justification for flight with

the single functional O-ring. It reported that tests showed the

Thiokol design should be retained, citing the Titan history, the leak

and hydroburst tests, and static motor firings as justification.

However, it also contained the following rationale which appeared to

conflict with the Criticality 1 classification that the secondary

O-ring was not redundant:
"Initial information generated in

a lightweight cylinder-to-cylinder proof test shows a total movement

of only .030 inch at pounds per square inch, gauge pressure in the

center joint. This . . . indicates that the tang-to-clevis movement

will not unseat the secondary O-ring at operating

pressures."
56
Testimony in hearings and statements given in

Commission interviews support the view that NASA management and

Thiokol still considered the joint to be a redundant seal even after

the change from Criticality 1R to 1. For example, McIntosh's

interview states:
Question

[After the Criticality I classification], what did you think it would

take to make [the joint seal] 1R?
Mr. McIntosh
: I thought it was already 1R. I thought that after

those tests that would have been enough to do it.
Question

Well, you knew it was 1 but you were hoping for 1R?
Mr McIntosh

Yeah, I was hoping for 1R, and I thought this test data would do it,

but it didn't.
57
At the time (in 1982-83), the redundancy of

the secondary O-ring was analyzed in terms of joint or hardware

geometry, with no consideration being given to the resiliency of the

ring as affected by temperatures.
58
Moreover, Marshall engineers like Ray and Miller

disagreed with Thiokol's calculations on the measurement of joint

opening.
59
That engineering debate eventually went to a "referee"

for testing which was not concluded until after the 51-L

accident.
127
] Notwithstanding the

view of some of Marshall engineers that the secondary ring was not

redundant, even at the time of the Criticality revision, Marshall

Solid Rocket Motor program management appeared to believe the seal

was redundant in all but exceptional cases. Dr. Judson Lovingood told

the Commission:
" . . . [T]here are two conditions

you have to have before you don't have redundancy. One of them is

what I call a spatial condition which says that the dimensional

tolerances have to be such that you get a bad stackup, you don't have

proper squeeze, etc. On the O-ring so that when you get joint

rotation, you will lift the metal surfaces off the O-ring. All right,

that's the one condition, and that is a worst case condition

involving dimensional tolerances.
"The other condition is a temporal condition

which says that you have to be past a point of joint rotation, and of

course, that relates back to what I just said.
"So first of all, if you don't have this bad

stackup, then you have full redundancy. Now, secondly, if you do have

the bad stackup, you had redundancy during the ignition transient up

to the 170 millisecond point, whatever it is, but that is the way I

understand the [Critical Items List]."
60
George Hardy and Lawrence Mulloy shared

Lovingood's view that the secondary seal was redundant in all but

situations of worst case tolerances.
61
However, there is no mention of this caveat in the

Critical Items List itself, nor does it appear in the subsequent

"waiver" of the Criticality 1 status granted by NASA Levels I and II

in March, 1983.
62
This waiver was approved to avoid the obligations

imposed on the Shuttle Program by Paragraph 2.8 of the Space Shuttle

Program Requirements Document, Level I, dated June 30, 1977. That

paragraph states:
"The redundancy requirements for

all flight vehicle subsystems (except primary structure, thermal

protection system, and pressure vessels) shall be established on an

individual subsystems basis, but shall not be less than fail-safe.

'Fail-safe' is defined as the ability to sustain a failure and retain

the capability to successfully terminate the mission. Redundant

systems shall be designed so that their operational status can be

verified during ground turnaround and to the maximum extent possible

while in flight."
63
Glynn Lunney, the former manager of the STS

Program (Level II at JSC) described the Criticality 1 change and

resulting waiver to the Commission on May 2:
Mr. Lunney
: Well, the approval of the waiver in March of 83, at

the time I was involved in that. I was operating on the assumption

that there really would be redundancy most of the time except when

the secondary O-ring had a set of dimensional tolerances add up, and

in that extreme case there would not be a secondary seal.
So I was dealing with what I thought was a

case where there were two seals unless the dimensional tolerances

were such that there might only be one seal in certain cases.
Chairman Rogers
: Now, to me, if you will excuse the expression, that

sounds almost contradictory, what you just said. What you first said

was you came to the conclusion that you could only rely on the

primary seal and therefore you removed the R.
Mr. Lunney

Yes, sir.
Chairman Rogers
: And now you're saying, if I understand it, that

experience showed that there was redundancy after all.
Mr. Lunney

No, I don't know of any experience showing that. What I'm saying is

that the removal of the R is an indicator that under all

circumstances we did not have redundancy. There were a certain number

of cases under which we would not have redundancy of the secondary

O-ring.
Recognizing that, even though there were a lot

of cases where we expected we would have redundancy we changed the

criticality designation.
Chairman Rogers
: It was saying to everybody else you can't necessarily

rely on the primary seal, and if the primary seal fails, as you've

said here, there may be loss of vehicle, mission and crew.
Mr. Lunney

I would adjust that to only say you cannot rely on the secondary

O-ring [
128
] but we would expect the primary O-ring to always be

there.
64
The criticality waiver was processed outside

the formal NASA Program Requirements Control Board, however,

representatives of that group "signed off" on the

document.
65
It was forwarded to Level I and approved by Associate

Administrator for Space Flight (Technical), L. Michael Weeks on March

28, 1983. Weeks told the Commission he signed the waiver because of

the Certification/Verification Review of the Propulsion Committee in

1980. Weeks explained, "We felt at the time-all of the people in the

program I think felt that this Solid Rocket Motor in particular or

the Solid Rocket Booster was probably one of the least worrisome

things we had in the program."
66
The waiver was signed less than one week prior to the

launch of STS-6 on April 4. According to interviews of Arnold Aldrich

and of Richard Kohrs, the latter having been involved with the waiver

review at Johnson Level II, the waiver was approved so that STS-6

could fly.
67
However, Weeks denied any connection between the Level

I waiver approval and the flight of STS-6.
68
Although some Thiokol engineers and officials

claimed that they had no notice of the Criticality change and waiver

in December, 1982 and in March, 1983, from the approval signatures

(including Thiokol's Operations Manager at Marshall, Maurice Parker)

and the distribution of the Criticality and Waiver documents,

apparently Thiokol officials were sent copies and were involved in

the criticality reclassification.
69
Nonetheless, the Commission has also determined that

several documents tracking the O-ring erosion at Thiokol and Marshall

refer to the Solid Rocket Motor field joint seal as Criticality 1-R,

long after the status was changed to Criticality 1.
70
STS 41-B O-Ring Erosion
As
Figure 2
shows,
71
prior to STS 41-B, the O-ring erosion/blow-by problem

was infrequent, occurring on a field joint of STS-2 (November, 1981),

nozzles of STS-6 (April, 1983) and a nozzle of QM-4 (March, 1983), a

qualification test motor fired by Thiokol.
72
However, when STS 41-B flew on February 3, 1984, the

left Solid Rocket Booster forward field joint and the right nozzle

joint primary O-rings both suffered erosion damage. Thiokol engineers

reacted to this discovery by filing a problem report on the O-ring

erosion found on STS 41 -B. Thiokol presented a series of charts to

the Marshall Solid Rocket Booster Engineering Office about the 41-B

O-ring erosion. Thiokol told Marshall that recent joint rotation

measurements in tests indicated the secondary O-ring will not unseat,

providing confidence that the secondary was an adequate backup. Keith

Coates described his view about Thiokol's data in a February 29, 1984

memorandum to George Hardy:
"We have two problems with their

rationale. The effect of 0.065 inch erosion on O-ring sealing

capability is not addressed. We have asked Thiokol to provide their

data to justify their confidence in the degraded O-ring. The second

concern is the amount of joint rotation. L. Ray does not agree with

Thiokol numbers, and he has action to discuss his concern with R.

Boisjoly (Thiokol) and reach agreement.
"Thiokol definition of their plans on

resolution of the problem is very weak."
The erosion problem was identified and tracked

by the Marshall Problem Assessment System as Marshall Record A07934

and by Thiokol as Thiokol Contractor Record DR4-5/30, "Slight char

condition on primary O-ring seal in forward field joint on SRM A57 of

STS-11 flight, Mission 41B."
73
The Marshall Problem Assessment System Report

states:
"Remedial action-none required;

problem occurred during flight. The primary O-ring seal in the

forward field joint exhibited a charred area approximately 1 inch

long .03-.050 inches deep and .100 inches wide. This was discovered

during post-flight segment disassembly at KSC."
A March 8, 1984 entry on the same report

continues:
"Possibility exists for some

O-ring erosion on future flights. Analysis indicates max erosion

possible is .090 inches according to Flight Readiness Review findings

for STS-13. Laboratory test shows sealing integrity at 3,000 psi

using an O-ring with simulated erosion depth of .095 inches

Therefore, this is not a constraint to future launches."
74
129-131
] Figure 2.
O-Ring Anomalies Compared with Joint

Temperature and Leak Check Pressure
Flight or

Motor
Date
(Solid Rocket

Booster)
Joint/O-Ring
Pressure

(psi)
Erosion
Blow-by
Joint Temp

°F
Field
Nozzle
DM-1
07/18/77
NA
NA
84
DM-2
01/18/78
NA
NA
49
DM-3
10/19/78
NA
NA
61
DM-4
02/17/79
NA
NA
40
QM-1
07/13/79
NA
NA
83
QM-2
09/27/79
NA
NA
67
QM-3
02/13/80
NA
NA
45
STS-1
04/12/81
50
50
66
STS-2
11/12/81
(Right)
Aft Field/Primary
50
50
70
STS-3
03/22/81
50
50
NA
NA
80
STS-4
06/27/82
Unknown: hardware lost at

sea
50
50
NA
NA
80
DM-5
10/21/82
NA
NA
58
STS-5
11/11/82
50
50
68
QM-4
03/21/83
Nozzle/Primary
NA
NA
60
STS-6
04/04/83
(Right)
Nozzle/Primary
50
50
67
(Left)
Nozzle/Primary
50
50
67
STS-7
06/18/83
50
50
72
STS-8
08/30/83
100
50
73
STS-9
12/28/83
100
100
70
STS 41-B
02/03/84
(Right)
Nozzle/Primary
200
100
57
(Left)
Forward

Field/Primary
200
100
57
STS 41-C
04/06/84
(Right)
Nozle/Primary
200
100
63
(Left)
Aft Field/Primary
200
100
63
(Right)
Igniter/Primary
NA
NA
63
STS 41-D
08/30/84
(Right)
Forward

Field/Primary
200
100
70
(Left)
Nozzle/Primary
200
100
70
(Right)
Igniter/Primary
NA
NA
70
STS 41-G
10/05/84
200
100
67
DM-6
10/25/84
Inner Gasket/Primary
NA
NA
52
STS 51-A
11/08/84
200
100
67
STS 51-C
01/24/85
(Right)
Center Field/Primary
200
100
53
(Right)
Center

Field/Secondary
200
100
53
(Right)
Nozzle/Primary
200
100
53
(Left)
Forward

Field/Primary
200
100
53
(Left)
Nozzle/Primary
200
100
53
STS 51-D
04/12/85
(Right)
Nozzle/Primary
200
200
67
(Right)
Igniter/Primary
NA
NA
67
(Left)
Nozzle/Primary
200
200
67
(Left)
Igniter/Primary
NA
NA
67
STS 51-B
04/29/85
(Right)
Nozzle/Primary
200
100
75
(Left)
Nozzle/Primary
200
100
75
(Left)
Nozzle/Primary
200
100
75
DM-7
05/09/85
Nozzle/Primary
NA
NA
61
STS 51-G
06/17/85
(Right)
Nozzle/Primary
200
200
70
(Left)
Nozzle/Primary
200
200
70
(Left)
Igniter/Primary
NA
NA
70
STS 51-F
07/29/85
(Right)
Nozzle/Primary
200
200
81
STS 51-I
08/27/85
(Left)
Nozzle/Primary
200
200
76
STS 51-J
10/03/85
200
200
79
STS 61-A
10/30/85
(Right)
Nozzle/Primary
200
200
75
(Left)
Aft Field/Primary
200
200
75
(Left)
Center Field/Primary
200
200
75
STS 61-B
11/26/85
(Right)
Nozzle/Primary
200
200
76
(Left)
Nozzle/Primary
200
200
76
STS 61-C
01/12/86
(Right)
Nozzle/Primary
200
200
58
(Left)
Aft Field/Primary
200
200
58
(Left)
Nozzle/Primary
200
200
58
STS 51-L
01/28/86
200
200
31
Dash (-) denotes no

anomaly.
NA denotes not

applicable.
NOTE: A list of the sequence of

launches (1-25), identified by STS mission designation, is provided

on pages 4 thru 6.
On STS-6, both nozzles had a hot gas path

detected in the putty with an indication of heat on the primary

O-ring.
On STS-9, one of the right Solid Rocket

Booster field joints was pressurized at 200 psi after a

destack.
On STS 41-C, left aft field had a hot gas

path detected in the putty with an indication of heat on the

primary O-ring.
On a center field joint of STS 51-C, soot

was blown by the primary and there was a heat effect on the

secondary.
On STS 51-G, right nozzle has erosion in

two places on the primary O-ring.
On STS 51-F, right nozzle had hot gas

path detected in putty with an indication of heat on the primary

O-ring.
On STS 51-I, left nozzle had erosion in

two places on the primary O-ring.
132
] This last entry is

also a summary of the briefing given by Thiokol to Lawrence Mulloy

about the 41-B erosion at the Level III Flight Readiness Review for

STS 41-C held at Marshall on March 8, 1984. At that same briefing,

the Chief Engineer for United Space Boosters, George Morefield,

raised prior Titan experience with O-ring problems. He explained in a

memorandum to Mulloy the following day:
"I alluded to the Titan III SRM

history which is quite similar to the current STS Solid Rocket Motor

experience. Post-fire inspection of Titan Solid Rocket Motor static

test motors showed that pressurization of the single O-rings in the

pressure vessel routinely occurred via a single break-down path

across the joint putty. There was also evidence that some O-rings

never see pressure in the Titan motor. The segment -to-segment case

insulation design results in a compression butt joint which

apparently is often sufficient to withstand Pc, ....
"Your review showed that there was sufficient

margin of O-ring remaining to do the job. I'm sure you have

considered that if it does burn through, the secondary O-ring will

then be similarly pressurized through a single port. So, some concern

remains.
"I recommend that you set up a panel to study

the use of putty and consider some alternatives:
"1) Is putty needed at all?
"2) If the tradition can't be broken, can the

putty be applied with multiple (6 or 8) pressurization paths built

in?
"I think that the primary seal should be

allowed to work in its classical design mode. Both the Titan and STS

Solid Rocket Motors have been designed for this not to happen. Titan

has flown over a thousand pressure joints with no failure. My opinion

is that the potential for failure of the joint is higher for the STS

Solid Rocket Motor, especially when occasionally the secondary seal

may not be totally effective."
75
When the 41-B erosion was taken to the Level I

Flight Readiness Review for 41-C on March 30, 1984, it was briefed as

a"technical issue". A recommendation to fly 41-C was approved by

Level I "accepting the possibility of some O-ring erosion due to the

hot gas impingement."
76
The rationale for acceptance was the same as that

given at the Level III Flight Readiness Review and entered into the

Marshall problem assessment report. An outgrowth of this review was

an April 5, 1984, directive from NASA Deputy Administrator Dr. Hans

Mark to Lawrence Mulloy at Marshall. This "Programmatic Action Item"

was signed by Weeks and asked Mulloy to conduct a "formal review of'

the Solid Rocket Motor case-to-case and case-to-nozzle joint sealing

procedures to ensure satisfactory consistent closeouts."
77
This action item had been preceded by a letter written

from NASA Associate Administrator for Space Flight General Abrahamson

to Marshall Center Director Lucas.
78
That letter, sent January 18, 1984, requested that

Marshall develop a plan of action to make improvement in NASA's

ability to design, manufacture and fly Solid Rocket Motors.

Abrahamson pointed out that NASA was flying motors where basic design

and test results were not well understood. The letter addressed the

overall general Solid Rocket Motor design but did not specifically

mention O-ring erosion.
After Mulloy received the April 5, 1984 STS

41-C action item on the O-rings, he had Lawrence Wear for-ward a

letter- to Thiokol which asked for a formal review of' the booster

field joint and nozzle joint sealing procedures. Thiokol was to

identify the cause of the erosion, determine whether it was

acceptable. define necessary changes, and reevaluate the putty then

in use. The Wear letter also requested small motor tests reflecting

joint dynamics as well as analysis of the booster assembly

process.
79
Thiokol replied to the Marshall STS 41-C

action item on May 4, 1984, with a program plan entitled "Protection

of' SRM Primary Motor Seals." The plan was prepared by Brian Russell,

then Thiokol's Manager of Systems Engineering. It outlined a

systematic program to isolate the 0-ring erosion and charring problem

and to eliminate damage to the joint seals.
80
Proposed areas of inquiry included the leak check

pressures, assembly loads, case eccentricity and putty layup. The

Thiokol response in May 1984 was merely a proposal. The actual final

response to the directive from Marshall was not completed until the

August 19, 1985 briefing on the Solid Rocket Motor seal held at NASA

headquarters some 15 months later.
81
133
Figure 3. Graphs depict flight anomaly

frequency for both field and nozzle joint of solid motors for a

variety of leak check pressures.
Leak Check and Putty
In addition to the action item from NASA

Headquarters, another result of the 41-B erosion was a warning

written by John Q. Miller, Marshall chief of the solid motor branch,

to George Hardy, through Keith Coates.
82
Miller was worried about the two charred rings on 41-B

and the "missing putty" found when the Solid Rocket Boosters were

recovered and disassembled. He specifically identified the putty's

sensitivity to humidity and temperature as potential sources of

problems. "The thermal design of the [Solid Rocket Motor] joints

depends on thermal protection of the O-ring by the [putty]," Miller

said. Failure of the putty to "provide a thermal barrier can lead to

burning both O-rings and subsequent catastrophic failure." The

memorandum also said that "the O-ring leak check procedure and its

potential effect on the (putty) installation and possible

displacement is also an urgent concern which requires expedition of

previously identified full scale tests."
From the beginning, Thiokol had suspected the

putty was a contributing factor in O-ring erosion, even after

STS-2.
83
In April 1983, Thiokol reported on tests conducted to

study the behavior of the joint putty. One conclusion of the report

was that the STS-2 erosion was probably caused by blow holes in the

putty, which allowed a jet of hot gas to focus on a point on the

primary O-ring. Thiokol discovered the focused jet ate away or

"impinged" on portions of the O-ring. Thiokol calculated that the

maximum possible impingement erosion was .090 inch, and that lab test

proved that an O-ring would seal at 3,000 psi when erosion of .095

inches was simulated. This "safety margin" was the basis for

approving Shuttle flights while accepting the possibility of O-ring

erosion.
84
Shortly after Miller's routing slip to Hardy

about the "urgent concern" of the missing putty on 41-B, at Thiokol,

Brian Russell authored a letter to Robert Ebeling which analyzed the

erosion history and the test data. Russell's April 9, 1984 conclusion

was that the putty itself and its layup were not at fault but that

the higher stabilization pressure adopted in leak check procedures,

first implemented in one field joint on STS-9, may increase the

chances of O-ring erosion. The conclusion by Miller and Russell was

that the air pressure forced through the joint during the O-ring leak

check was creating more putty blow holes, allowing more focused jets

on the primary O-ring, thereby increasing the frequency of

erosion.
85
This hypothesis that O-ring erosion is related

to putty blow holes is substantiated by the leak check history

Figure 3
). Prior to January, 1984, and STS 41-B, when the leak

check pressure was [
134
] 50 or 100 psi, only one field joint O-ring anomaly

had been found during the first nine flights. However, when the leak

check stabilization pressure was officially boosted to 200 psi for

STS 41-B, over half the Shuttle missions experienced field joint

O-ring blow-by or erosion of some kind.
86
Moreover, the nozzle O-ring history of

problems is similar. The nozzle joint leak check was changed from 50

psi to 100 psi before STS-9 launched in November 1983. After this

change, the incidence of O-ring anomalies in the nozzle joint

increased from 12 percent to 56 percent of all Shuttle flights. The

nozzle pressure was increased to 200 psi for mission 51-D in April,

1985, and 51-G in June, 1985, and all subsequent missions. Following

the implementation of the 200 psi check on the nozzle, 88 percent of

all flights experienced erosion or blow-by.
87
Both Thiokol and NASA witnesses agreed that

they were aware that the increase in blow holes in the putty could

contribute to O-ring erosion. The Commission testimony of May 2,

1986, reads:
Dr. Walker
: The analysis that some of our staff has done suggests

that after you increase the test pressure to 200 pounds, the

incidence of blow-by and erosion actually increased.
Mr. Russell

We realized that.
Lawrence Mulloy was also questioned above the

blow holes in the putty:
Dr. Walker
: Do you agree that the primary cause of the erosion is

the blow holes in the putty?
Mr. Mulloy

I believe it is. Yes.
Dr. Walker

And so your leak check procedure created blow holes in the

putty?
Mr. Mulloy

That is one cause of blow holes in the putty.
Dr. Walker

But in other words, your leak check procedure could indeed cause what

was your primary problem. Didn't that concern you?
Mr. Mulloy

Yes, sir.
88
Notwithstanding the knowledge that putty blow

holes caused erosion and that higher pressure in the leak check

caused more blow holes, Thiokol recommended and NASA accepted the

increased pressure to ensure that the joint actually passed the

integrity tests.
89
The documentary evidence produced by NASA and

Thiokol demonstrates that Marshall was very concerned about the putty

erosion/blow hole problem after STS 41-B. In addition to John

Miller's routing slip about putty on STS 41-B discussed above, there

is a report of a June 7, 1984, telephone conference between Messrs.

Thompson, Coates and Ray (Marshall) and Messrs. Sayer, Boisjoly,

Russell and Parker (Thiokol), among others.
90
Marshall told Thiokol that NASA was very concerned

about the O-ring erosion problem and that design changes were

necessary, including possible putty changes. The Thiokol engineers

discussed Marshall's suggestions after the telephone conference, but

decided they could not agree a change was mandatory. A follow-up

telephone conference was held between Ben Powers of Marshall and

Lawrence Sayer of Thiokol on July 2. Powers told Saver that NASA

would not accept the removal of the putty from the joint and that

everyone expected the tests to show that gas jets would damage an

O-ring. However, Powers expressly stated that Marshall would not

accept Thiokol's opinion that no further tests were necessary.
In mid-1984, the early tests after NASA's

action item for 41-C led Thiokol to the conclusion that O-ring

erosion was a function of the putty blow hole size and the amount of

free volume between the putty orifice and the O-ring. The damage to

the O-ring was judged to be worse when the blow hole was smaller and

the free volume was larger.
91
While Thiokol did establish plans for putty

tests to determine how it was affected by the leak check in response

to the 41-C action item, their progress in completing the tests was

slow. The action item was supposed to be completed by May 30, 1984,

but as late as March 6, 1985, there are Marshall internal memos that

complain that Thiokol had not taken any action on Marshall's December

1983 directive to provide data on putty behavior as affected by the

joint leak check stabilization pressure.
92
STS 51-C and Cold Temperature
On January 24, 1985, STS 51-C was launched.

The temperature of the O-rings at launch was 53....
135
] Figure 4.
NASA Official
Position
Description of Awareness of O-Ring

Problems
John Young
Chief, Astronaut Office
"The secret seal, which no one that

we know knew about."
93
Milton Silveira
Chief Engineer
". . .If I had known . . . I'm sure

in the '82 time period when we first came to that conclusion

[that the seal was not redundant], I would have insisted

that we get busy right now on a design change and also look

for any temporary fix we could do to improve the operation

of the seal. "
94
James Beggs
(Former) NASA Administrator
"I had no specific concerns with the

joint, the O-rings or the putty...."
95
Arnold Aldrich
Manager, National Space

Transportation System
None were aware of Thiokol's concern

about negative effect of cold temperature on O-ring

performance, nor were they informed of the same concern

raised after STS 51-C.
96
Jesse Moore
(Former) Associate Administrator for

Space Flight
Richard Smith
Director, Kennedy Space Center
James A. Thomas
Deputy Director, Kennedy Launch and

Landing Operations
....degrees, the coldest to that date. O-ring

erosion occurred in both solid boosters. The right and left nozzle

joint showed evidence of blow-by between the primary and secondary

O-rings. The primary O-ring in the left booster's forward field joint

was eroded and had blow-by, or soot behind the

ring.
97
The right booster's damage was in the center field

joint-the first time that field joint seal was damaged. Both its

primary and secondary O-rings were affected by heat, and the primary

ring also had evidence of blow-by of soot behind it. This was also

the first flight where a secondary O-ring showed the effect of

heat.
STS 51-C was the second example of O-ring

damage in flight where there was evidence of blow-by erosion as well

as impingement erosion. As noted previously, impingement erosion

occurs where the O-ring has already sealed and a focused jet of hot

gas strikes the surface of the ring and removes a portion of it.

Blow-by erosion happens when the O-ring has not yet sealed the joint

gap and the edge of the ring erodes as the hot gas flows around

it.
Roger Boisjoly described the blow-by erosion

seen in 51-C:
"SRM 15 [STS 51-C] actually

increased [our] concern because that was the first time we had

actually penetrated a primary,, O-ring on a field joint with hot gas,

and we had a witness of that event because the grease between the

O-rings was blackened just like coal . . . and that was so much more

significant than had ever been seen before on any blow-by on any

joint . . . the fact was that now you introduced another phenomenon.

You have impingement erosion and bypass erosion, and the O-ring

material gets removed from the cross section of the O-ring much, much

faster when you have bypass erosion or blow-by."
98
136
] Boisjoly also said

blow-by erosion was where the primary O-ring "at the beginning of the

transient cycle . . . is still being attacked by hot gas, and it is

eroding at the same time it is trying to seal, and it is a race

between, will it erode more than the time allowed to have it seal."

He described the blow-by on 51-C as "over 100 degrees of arc, and the

blow-by was absolutely jet black. It was totally intermixed in a

homogeneous mixture in the grease." When the blow-by material was

chemically analyzed, Boisjoly said, "we found the products of putty

in it, we found the products of O-ring in it."
99
On the Marshall problem assessment report that

was started to track field joint erosion after STS 41-B, the STS 51

-C O-ring anomaly was described as "O-ring burns were as bad or worse

than previously experienced . . . Design changes are pending test

results."
100
The changes being considered included modifying the

O-rings and adding grease around the O-rings to fill the void left by

putty blow holes.
On January 31, 1985, Marshall Solid Rocket

Booster Project Manager Mulloy sent an urgent message to Lawrence

Wear with the stated subject: "51-C O-Ring Erosion Re: 51-E FRR." The

message ordered that the Flight Readiness Review for the upcoming

flight:
"Should recap all incidents of

O-ring erosion, whether nozzle or case joint, and all incidents where

there is evidence of flow past the primary O-ring. Also, the

rationale used for accepting the condition on the nozzle O-ring.

Also, the most probable scenario and limiting mechanism for flow past

the primary on the 51 -C case joints. If [Thiokol] does not have all

this for today I would like to see the logic on a chart with blanks

[to be filled in ] . "
101
On February 8, 1985, Thiokol presented its

most detailed analysis to date of the erosion problems to the Solid

Rocket Motor project office at Marshall for what was then called

Shuttle mission 51-E, but later changed to 51-D. Thiokol included a

report on damage incurred by the O-rings during flight 51-C at the

left forward and right center field joints. The right center joint

had hot gas past the primary O-ring. Thiokol said that caused a

concern that the gas seal could be lost, but its resolution was

"accept risk."
102
Thiokol presented test results showing

"maximum expected erosion" and "maximum erosion experienced" for both

primary and secondary O-rings for- the field and nozzle joints.

Accepting damage to the primary O-ring was being justified, in part,

based on an assumption of the secondary O-ring working even with

erosion. However, the Criticality classification indicated the

primary seal was a "single point failure." During this flight

readiness assessment at Marshall, for the first time Thiokol

mentioned temperature as a factor in O-ring erosion and blow-by.

Thiokol said in its conclusions that "low temperature enhanced

probability of blow-by-[flight] 51 -C experienced worst case

temperature change in Florida history." Thiokol concluded that while

the next Shuttle flight "could exhibit same behavior," nonetheless

"the condition is not desirable but is acceptable."
103
At the Level I Flight Readiness Review

conducted on February 21, there was no detailed analysis of O-ring

problems presented or any reference made to low temperature effects.

Instead, a single reference indicated the O-ring erosion and blow-by

experienced was "acceptable" because of 'limited exposure time and

redundancy."
STS 51-B and the Launch

Constraint
Joint seal problems occurred in each of the

next four Shuttle flights. Flight 51-D, launched April 12, 1985 had

nozzle O-ring erosion and blow-by on an igniter joint. STS 51-B,

launched 17 days later, experienced both nozzle O-ring erosion and

blow-by as did 51-G, which flew on the following June 17. STS 51-F,

launched duly 29, 1985 had nozzle O-ring blow-by.
104
In response to the apparent negative effect of

cold leading to the extensive O-ring problems on flight 51 -C in

January, Thiokol conducted some O-ring resiliency tests in early

1985.
105
The tests were conducted to quantify the seal timing

function of the secondary O-ring and the effect of joint rotation on

its ability to back up the primary ring. The key variable was

temperature. The June 3 test report, which was described in an August

9, 1985 letter from Brian Russell at Thiokol to Jim Thomas at

Marshall, showed:
"Bench test data indicates that

the O-ring resiliency (its capability to follow the metal) is a

function of temperature and rate of case expansion. [Thiokol]

measured the force of the O-ring against Instron platens, which

137

simulated the nominal squeeze on the O-ring and approximated the case

expansion distance and rate.
"At 100°F, the O-ring maintained contact.

At 75°F the O-ring lost contact for 2.4 seconds. At 50°F,

the O-ring did not reestablish contact in ten minutes at which time

the test was terminated."
106
On June 25, 1985, the left nozzle joint of STS

51-B (launched April 29) was disassembled and inspected after it had

been shipped back to Thiokol. What Thiokol found was alarming. The

primary O-ring seal had been compromised because it eroded .171

inches and it did not seal. The secondary O-ring did seal, but it had

eroded .032 inches. Lawrence Mulloy described the 51-B problem as

follows:
"This erosion of a secondary

O-ring was a new and significant event . . . that we certainly did

not understand. Everything up to that point had been the primary

O-ring, even though it had experienced some erosion does seal. What

we had evidence of was that here was a case where the primary O-ring

was violated and the secondary O-ring was eroded, and that was

considered to be a more serious observation than previously observed

. . .
107
"What we saw [in 51-B], it was evident that

the primary ring never sealed at all, and we saw erosion all the way

around that O-ring, and that is where the .171 came from, and that

was not in the model that predicated a maximum of .090, the maximum

of .090 is the maximum erosion that can occur if the primary O-ring

seals.
"But in this case, the primary O-ring did not

seal; therefore, you had another volume to fill, and the flow was

longer and it was blow-by and you got more erosion."
108
Upon receiving the report of the 51-B primary

ring failure, Solid Rocket Booster Project Manager Mulloy and the

Marshall Problem Assessment Committee placed a "launch constraint" on

the Shuttle system.
109
A 1980 Marshall letter which references "Assigning

Launch Constraints on Open Problems Submitted to MSFC PAS" defines

launch constraint as:
"All open problems coded

Criticality 1, 1R, 2, or 2R will be considered launch constraints

until resolved (recurrence control established and its implementation

effectivity determined) or sufficient rationale, i.e., different

configuration, etc., exists to conclude that this problem will not

occur- on the flight vehicle during pre-launch, launch, or flight."
110
Lawrence Mulloy told the Commission that the

launch constraint was "put on after we saw the secondary O-ring

erosion on the [51-B] nozzle." "Based on the amount of charring," the

problem report listing the constraint said, "the erosion paths on the

primary O-ring and what is understood about the erosion phenomenon,

it is believed that the primary O-ring [of the joint] never sealed."
111
The constraint applied to STS 51-F and all flights

subsequent, including STS 51-L. Although one Marshall document says

that the constraint applied to all O-ring anomalies,
112
no similar launch constraint was noted on the Marshall

Problem Assessment Report that started tracking the field joint

erosion after STS 41-B. Thiokol officials who testified before the

Commission all claimed they were not aware of the July 1985 launch

constraint;
113
however, Thiokol letters referenced Marshall Record

number A09288, the report that expressly identified the constraint.
114
After the launch constraint was imposed,

Project Manager Mulloy waived it for each Shuttle flight after July

10, 1985. Mr. Mulloy and Mr. Lawrence Wear outlined the procedure in

the following manner:
Chairman Rogers
: To you, what does a constraint mean, then?
Mr. Mulloy

A launch constraint means that we have to address the observations,

sec if we have seen anything on the previous flight that changes our

previous rationale and address that at the Flight Readiness

Review.
Chairman Rogers
: When you say»address it," I always get confused

by the word. Do you mean think about it? Is that what you

mean?
Mr. Mulloy

No, sir. I mean present the data as to whether or not what we have

seen in our most recent observation, which may not be the last

flight, it may be the flight before that, is within our experience

base and whether or not the previous analysis and [
138
] tests that

previously concluded that was an acceptable situation is still valid,

based upon later observations....
The constraint was put on after we saw the

secondary O-ring erosion on the nozzle, I believe.
Chairman Rogers
: Who decided that?
Mr. Mulloy

I decided that, that that would be addressed, until that problem was

resolved, it would be considered a launch constraint, and addressed

at Flight Readiness Reviews to assure that we were staying within our

test experience base....
Chairman Rogers
: Do you have ultimate responsibility for waiving the

launch constraints?
Mr. Mulloy

Yes, sir, I have ultimate responsibility for the launch readiness of

the Solid Rocket Boosters.
Chairman Rogers:
So there was a launch constraint, and you waived

it.
Mr. Mulloy

Yes, sir-, all flights subsequent to.
Dr. Ride

I'm trying to understand how you deal with the launch constraint. How

important do you think a launch constraint is and how unusual is it

in your system?
Mr. Wear
: I

think a launch constraint is a significant event in our system, and

it is one that has to be addressed within the Flight Readiness cycle

because I don't have the authority to not do that. .
Dr. Ride

Why didn't you put a launch constraint on the field joint at the same

time?
Mr. Mulloy

I think at that point, and I will react to that question in real

time, because I haven't really thought about it, but I think the

logic was that we had been observing the field joint, the field and

nozzle joint primary O-ring erosion. This erosion of a secondary

O-ring was a new and significant event, very new and significant even

that we certainly did not understand. Everything up to that point had

been that the primary O-ring, even though it had experienced some

erosion, does seal. What we had evidence of was that here was a case

where the primary O-ring was violated and the secondary O-ring was

eroded, and that was considered to be a more serious observation than

previously observed.
Dr. Ride

Correct me if I am wrong, but weren't you basing most of your

decisions on the field joint on analysis of what was the maximum,

what you believed to be the maximum possible erosion, and you had

that analysis for the field joint and for the nozzle joint. When you

saw the complete erosion of the primary O-ring on the nozzle joint,

that showed you that your analysis on the nozzle joint wasn't any

good, I would think. That would indicate to you that your analysis on

the field joint wasn't very good, either, or at least should be

suspect.
Mr. Mulloy

The conclusion, rightly or wrongly, for the cause of the secondary

O-ring erosion on the nozzle joint, it was concluded from test data

we had that 100 psi pressurization leak check, that the putty could

mask a primary O-ring that was not sealing. The conclusion was-and

that one was done at 100 psi. The conclusion was that in order to get

that type of erosion that we saw on the primary O-ring, that that

O-ring never sealed, and therefore the conclusion was that it never

was capable of sealing. The leak check on subsequent nozzles, all

subsequent nozzles was run at 200 psi, which the test data indicated

would always blow through the putty, and in always blowing through

the putty we were guaranteed that we had a primary O-ring seal that

was capable of sealing, and then we further did, and we already had

that on the field joints at that time.
115
While Mulloy and Wear both testified that the

constraint was still in effect and waived for Challenger's flight,

they told the Commission that there had been two erroneous entries on

the O-ring erosion nozzle problem assessment report stating the

O-ring erosion problem had been resolved or closed.
116
Thiokol had suggested this closure on December 10,

1985 (at Marshall's request according to Brian Russell) but Wear and

Mulloy told the Commission they rejected that recommendation and the

problem was still being addressed in Flight Readiness

Reviews.
117
NASA Levels I and II apparently did not realize

Marshall had assigned a launch constraint within the Problem

Assessment System.
118
This......
139
Figure 5. August 19,1985 Headquarters

Briefing.
General Conclusions
Recommendations
All O-ring erosion has occurred

where gas paths in the vacuum putty are formed
Gas paths in the vacuum putty can

occur during assembly, leak check, or during motor

pressurization
Improved filler materials or

layup configurations which still allow a valid leak check

of the primary O-rings may reduce frequency of O-ring

erosion but will probably not eliminate it or reduce the

severity of erosion
Elimination of vacuum putty in a

tighter joint area will eliminate O-ring erosion if

circumferential flow is not present-if it is present,

some baffle arrangement may be required
Erosion in the nozzle joint is

more severe due to eccentricity; however, the secondary

seal in the nozzle will seal and will not erode

through
The primary O-ring in the field

joint should not erode through but if it leaks due to

erosion or lack of sealing the secondary seal may not

seal the motor
The igniter Gask-O-Seal design is

adequate providing proper quality inspections are made to

eliminate overfill conditions
The lack of a good secondary seal

in the field joint is most critical and ways to reduce

joint rotation should be incorporated as soon as possible

to reduce criticality
The flow conditions in the joint

areas during ignition and motor operation need to be

established through cold flow modeling to eliminate

O-ring erosion
QM-5 static test should be used

to qualify a second source of the only flight certified

joint filler material (asbestos-filled vacuum putty) to

protect the flight program schedule
VLS-1 should use the only flight

certified joint filler material (Randolph asbestos-filled

vacuum putty) in all joints
Additional hot and cold subscale

tests need to be conducted to improve analytical modeling

of O-ring erosion problem and for establishing margins of

safety for eroded O-rings
Analysis of existing data

indicates that it is safe to continue flying existing

design as long as all joints are leak checked with a 200

psig stabilization pressure, are free of contamination in

the seal areas and meet O-ring squeeze

requirements
Efforts need to continue at an

accelerated pace to eliminate SRM seal erosion
......communication failure was contrary to

the requirement, contained in the NASA Problem Reporting and

Corrective Action Requirements System, that launch constraints were

to be taken to Level II.
Escalating Concerns
When the burn through of the primary nozzle

O-ring on the left Solid Rocket Booster of STS 51-B was discovered in

Utah on dune 25, 1985, an engineer from the NASA headquarters Shuttle

Propulsion Group was on the scene. Three days after the 51-B

inspection, a memorandum was written to Michael Weeks, also at

Headquarters, reporting on the primary O-ring burn

through.
119
The memo blamed the problem on the faulty 100 psi leak

check and reminded Weeks that Thiokol had not yet responded to the

O-ring erosion action item sent out after STS 41-B one year

earlier.
Engineers at Thiokol also were increasingly

concerned about the problem. On July 22, 1985, Roger Boisjoly of the

structures section wrote a memorandum predicting NASA might give the

motor contract to a competitor or there might be a flight failure if

Thiokol did not come up with a timely solution.
120
Nine days later (July 31) Boisjoly wrote

another memorandum titled "O-ring Erosion/Potential Failure

Criticality" to R. K. Lund, Thiokol's Vice President of

Engineering:
"The mistakenly accepted position

on the joint problem was to fly without fear of failure and to run a

series of design evaluations which would ultimately lead to a

solution or at least a significant reduction of the erosion problem.

This position is now changed as a result of the [51-B] nozzle joint

erosion which eroded a secondary O-ring with the primary O-ring never

sealing. If the same scenario should occur in a field joint (and it

could), then it is a jump ball whether as to the success or failure

of the joint because the secondary O-ring cannot respond to the

clevis opening rate and may not be capable of pressurization. The

result would be a catastrophe of the highest order-loss of human

life."
Boisjoly recommended setting up a team to

solve the O-ring problem, and concluded by stating:
"It is my honest and very real

fear that if we do not take immediate action to dedicate a team to

solve the problem, with the field joint having the number one

priority, then we stand in jeopardy of losing a flight along with all

the launch pad facilities."
121
140
] In reply to

specific questions from Marshall on August 9, Thiokol's Brian Russell

reported the test data on the dune 3 resiliency tests. As noted

previously, he indicated O-ring resiliency was a function of the

temperature and case expansion. Also, he wrote, Thiokol had no reason

to suspect that the primary O-ring would fail after motor ignition

transient. He said the secondary O-ring would seal within the period

after ignition from 0 to 170 milliseconds.
122
From 170 to 330 milliseconds, the probability of the

sealing of the secondary O-ring was reduced. From 330 to 600

milliseconds, there was only a slight chance the secondary seal would

hold.
On August l9, 1985, Thiokol and Marshall

program managers briefed NASA Headquarters on erosion of the motor

pressure seals.
123
The briefing paper concluded that the O-ring seal was

a critical matter, but it was safe to fly. The briefing was detailed,

identifying all prior instances of field joint, nozzle joint and

igniter O-ring erosion. It recommended an "accelerated pace" to

eliminate seal erosion but concluded with the recommendation that "it

is safe to continue flying existing design as long as all joints are

leak checked with a 200 psig stabilization pressure, are free of

contamination in the seal areas and meet O-ring squeeze

requirements." The briefing conclusions and recommendations appear in
Figure 5
124
Thiokol's Robert Lund, Vice

President-Engineering, noting that "the result of a leak at any of

the joints would be catastrophic," announced the establishment of a

Thiokol O-ring task force on August 20, 1985, to "investigate the

Solid Rocket Motor case and nozzle joints, both materials and

configurations, and recommend both short-term and long-term

solutions."
125
Two days later, A. R. Thompson, Thiokol's

supervisor of structures design, said in a memorandum to S. R. Stein,

project engineer, that the "O-ring seal problem has lately become

acute." Thompson recommended near-term solutions of increasing the

thickness of shims used at the tang and clevis mating, and increasing

the diameter of the O-ring. "Several long-term solutions look good;

but, several years are required to incorporate some of them,"

Thompson wrote. "The simple short-term measures should be taken to

reduce flight risks."
126
During a Commission hearing, Thompson was asked about

the larger diameter O-ring solution:
Dr. Walker
: Why didn't you go to the larger O-ring, then?
Mr. Thompson
: One problem in going to larger O-rings is in field

joints-plant joints, excuse me. In the plant joints, if you put in

the 295 and you take the worst on worst, when the joint is raised to

a temperature of 325 degrees during the curing of the insulation, it

is an overfill condition because of the alpha problems with the case,

and the rubber.
Dr. Walker

There is no reason why a field joint and a plant joint had to have

the same O-ring, is there?
Mr. Thompson
: There were some that were afraid of the QC people,

that were afraid of the confusion that might be developed between two

nearly the same sized O-ring.
127
Thiokol's revised O-ring protection plan,

dated August 30, 1985, indicated that NASA and Thiokol were still not

in agreement on the magnitude of the joint rotation phenomenon. It

said that "presently there are conflicting data from Solid Rocket

Motor case hydrotest and [static tests] concerning the magnitude of

case field joint rotation under motor pressure. A referee test will

be devised, which is mutually acceptable to NASA and Thiokol, to

determine joint opening characteristics."
128
Design Questions Resurface
Also in late August, Thiokol submitted

"Preliminary Solid Rocket Motor Nozzle/Field Joint Seal Concepts" to

NASA, which were "formulated to solve the [Solid Rocket Motor]

sealing problems." The document contained 43 possible design concepts

for field joints and 20 for nozzle joints. The report said Thiokol

"feels the case field joint poses the greatest potential risk in that

its secondary seal may not maintain metal contact throughout motor

operation. The nozzle joint is also of major concern because the

frequency and severity of seal damage experienced has been greater

than any other joint."
In September 1985, Thiokol's plans called for

test-firing a static motor with various O-ring configurations. In a

September 10 presentation to Marshall, Thiokol discussed erosion

predictions, and evaluated primary engineering concerns including

joint deflection and secondary O-ring resiliency. Temperature was not

mentioned.
129
141
] Prior to that

Thiokol presentation, Marshall Science and Engineering Director

Kingsbury had informed Solid Rocket Booster Program Manager

Mulloy:
"I am most anxious to be briefed

on plans for improving the Solid Rocket Motor O-ring seals.

Specifically, I want to review plans which lead to flight

qualifications and the attendant schedules. I have been apprised of

general ongoing activities but these do not appear to carry the

priority which I attach to this situation. I consider the O-ring seal

problem on the Solid Rocket Motor to require priority attention of

both Morton Thiokol/Wasatch and MSFC."
130
Early in October, internal warnings about the

lack of results from the O-ring task force came when Thiokol's

management got two separate memoranda complaining about

administrative delays and lack of cooperation. One memorandum was

written by Roger Boisjoly on October 4, 1985, and it warned Thiokol

management about lack of management support of the O-ring team's

efforts.
131
He said that "even NASA perceives that the team is

being blocked in its engineering efforts to accomplish its task. NASA

is sending an engineering representative to stay with us starting

October 14th. We feel that this is the direct result of their feeling

that we [Thiokol] are not responding quickly enough on the seal

problem."
R. V. Ebeling, manager of Thiokol's Solid

Rocket Motor ignition system, began his October 1, 1985, report to

McDonald with the alarming word "HELP!" Ebeling said the seal task

force was "constantly being delayed by every possible means."

"Marshall Space Flight Center," he said, "is correct in stating that

we do not know how to run a development program." Ebeling

continued:
"The allegiance to the O-ring

investigation task force is very limited to a group of engineers

numbering 8-10. Our assigned people in manufacturing and quality have

the desire, but are encumbered with other significant work. Others in

manufacturing, quality, procurement who are not involved directly,

but whose help we need, are generating plenty of resistance. We are

creating more instructional paper than engineering data. We wish we

could get action by verbal request, but such is not the case. This is

a red flag."
132
Shuttle flight 61-A was launched October 30,

1985. It experienced nozzle O-ring erosion and field joint O-ring

blow-by.
133
These anomalies were not mentioned at the Level I

Flight Readiness Review for flight 61-B. That flight was launched on

November 26, 1985, and sustained nozzle O-ring erosion and blow-by.
134
The following month (December) Thiokol's

problem status report which tracked the field joint erosion anomaly

stated that the O-ring task force had made one hot gas test and

preliminary results indicated the test chamber needed to be

redesigned.
135
Mr. Ebeling of Thiokol became so concerned about the

gravity of the O-ring problem that he told fellow members of the seal

task force that he believed Thiokol should not ship any more motors

until the problem was fixed.
In testimony before the Commission, Ebeling

said:
Mr. Ebeling
: Well, I am a hydraulics engineer by profession, and

O-rings and seals and hydraulics are very sacred, but for the most

part, a hydraulics or pneumatics engineer controls the structure, the

structural design, the structural deformation to make sure that this

neat little part that is so critical is given every thing it needs to

operate. In Solid Rocket Motors I have been there now pushing 25

years. They had a different attitude on O-rings when I came there,

and it is not just Thiokol, it is universal.
Dr. Covert

By universal, you mean the solid rocket industry?
Mr. Ebeling

The entire solid rocket industry. It gets around from one, the

competitors' information eventually gets to me by one track or

another, and mine to them, but my experience on O-rings was and is to

this date that the O-ring is not a mechanism and never should be a

mechanism that sees the heat of the magnitude of our motors, and I

think before I do retire, I'm going to make sure that we discontinue

to fly with round seals which I am against round seals anyway. I

think seals with memories, not pressure-activated, but energized

through mechanical means, and in all cases, keep the heat of our

rocket [
142
] motors away from those seals. Whatever it is, you do

not need chamber pressure to energize a seal.
Dr. Covert

In this regard, then, did you have an increasing concern as you saw

the tendency first to accept thermal distress and then to say, well,

we can model this reasonably and we can accept a little bit of

erosion, and then etc., etc. ? Did this cause you a feeling of if not

distress, then betrayal in terms of your feeling about

O-rings?
Mr. Ebeling

I'm sure sorry you asked that question.
Mr. Covert

I'm sorry I had to.
Mr. Ebeling

To answer your question, yes. In fact, I have been an advocate, I

used to sit in on the O-ring task force and was involved in the seals

since Brian Russell worked directly for me, and I had a certain

allegiance to this type of thing anyway, that I felt that we

shouldn't ship any more rocket motors until we got it fixed.
Dr. Covert

Did you voice this concern?
Mr. Ebeling

Unfortunately, not to the right people.
136
The Closure Issue
On December 6, 1985, Thiokol's Brian Russell

wrote Al McDonald, Thiokol Solid Rocket Motor Project Director,

requesting "closure of the Solid Rocket Motor O-ring erosion critical

problems."
137
He gave 17 reasons for the closure, including test

results, future test plans and the work to date of Thiokol's task

force. Four days later (December 10) McDonald wrote a memorandum to

NASA's Wear asking for closure of the O-ring problem. All O-ring

erosion problems, including the problem containing the July 1985

launch constraint, were among the referenced matters that Thiokol

suggested should be closed. McDonald noted that the O-ring problem

would not be fully resolved for some time, and he enclosed a copy of

Thiokol's August 30 plan for improving the motor

seals.
138
Brian Russell described the problem tracking

process and gave the reason for the closure recommendation during the

following exchange:
Mr. Russell
: We have our reliability engineering department, who

is responsible to complete the monthly problem report, and in

addition to that we have our monthly problem review board telephone

conference with NASA and the contractors, of which we are a part, and

the monthly problem review or the monthly problem report that

reliability prepares, they get the information from engineering or

from the office as necessary to complete their status of what has

happened during that month, whether the problem originated that month

or what has been done to close the problem out, and that is submitted

every month, and I for one do review that before it is submitted to

the Marshall Space Flight Center, and so much of the information that

I would read in these reports would be the same information that we

had given in that monthly problem report or over the telephone on the

teleconference.
Chairman Rogers
: Mr. Russell, when you say close the problem out, what

do you mean by that? How do you close it out normally?
Mr. Russell

Normally, whether it takes engineering analysis or tests or some

corrective action, a closeout to the problem would occur after an

adequate corrective action had been taken to satisfy those on the

problem review board that the problem had indeed been closed out.

That is the way that that happens; for example, we had found a loose

bolt on the recovery one time, and we had to take corrective action

in our procedures and in the engineering to make sure that that

wouldn't happen again, and then to verify that corrective action, and

at that point that problem would be ready to be closed out. It

generally involves a report or at least a mention by the review board

stating what had been done to adequately close it out, and then it is

agreed upon by the parties involved. .
Question

What do you understand a launch constraint to mean?
Mr. Russell

My understanding of a launch constraint is that the launch cannot

proceed without adequately-without everyone's agreement that the

problem is under control.
143
Chairman Rogers
: Under

control meaning what? You just said a moment ago that you would

expect some corrective action to be taken.
Mr. Russell

That is correct, and in this particular case on this 51-B nozzle

O-ring erosion problem there had been some corrective action taken,

and that was included in the presentation made as a special addendum

to the next Flight Readiness Review, and at the time we did agree to

continue to launch, which apparently had lifted the launch

constraint, would be my understanding.
Chairman Rogers
: But really my question is: Did you gentlemen realize

that it was a launch constraint?
Mr. Russell

I would like to answer for myself. I didn't realize that there was a

formal launch constraint on this one, any different than some of the

other erosion and blow-by that we had seen in the past.
Mr. Ebeling

I agree. .
Question
: .

. . Mr. Russell, you wrote a letter, did you not, or a memorandum

indicating that the problem should be closed.
Could you explain to the Commission what you

meant by that?
Mr. Russell

Yes. In our December telephone call on the Problem Review Board-and I

can't remember the date-it was around the 9th or so-there was a

request to close the problems out and particularly the ones that had

been open for a long time, of which this was one, and a long time

meaning six months or more.
There was a request from the Director of

Engineering, as I recall it, that we close these problems out.

Dr. Walker

That was the Director of Engineering at Marshall?
Mr. Russell

Yes, at Marshall Space Flight Center. Now, he wasn't in that call. My

understanding is what they told us and my recollection was that Mr.

Kingsbury would like to see these problems closed out.
Now, the normal method of closing them out is

to implement the corrective action, verify the corrective action, and

then the problem is closed, it comes off the board and is no longer

under active review. .
Chairman Rogers
: What was being done to fix it?
Mr. Russell

Well, we had a task force created of full-time people at Thiokol, of

which I was a member of that task team, and we had done some

engineering tests. We were trying to develop concepts. We had

developed some concepts to block the flow of hot gas against the

O-ring to the point where the O-ring would no longer be damaged in a

new configuration.
And we had run some cold gas tests and some

hot gas motor firing tests and were working toward a solution of the

problem and we had some meetings scheduled with the Marshall Space

Flight Center. We had weekly telephone calls where we statused our

progress and there was a team at Marshall also of engineering people

who were monitoring the things that we were doing to fix the problem

with the goal of implementing a fix in our qualification motor No. 5,

which was scheduled at that time in January, this timeframe being

about the December timeframe of last year.
Chairman Rogers
: Can I interrupt? So you're trying to figure out how

to fix it, right? And you're doing some things to try to help you

figure out how to fix it.
Now, why at that point would you close it out?

Mr. Russell

Because I was asked to do it.
Chairman Rogers
: I see. Well, that explains it.
Mr. Rummel

It explains it, but really doesn't make any sense. On one hand you

close out items that you've been reviewing flight by flight, that

have obviously critical implications, on the basis that after you

close it out, you're going to continue to try to fix it.
So I think what you're really saying is,

you're closing it out because you don't want to be bothered. Somebody

doesn't want to be bothered with flight-by-flight reviews, but you're

going to continue to work on it after it's closed out.
139
144
] Marshall received

the Thiokol letter asking for the closure and an entry was placed on

all Marshall Problem Reports referenced in McDonald's December 10

letter indicating"contractor closure received" on December 18, 1985.
140
On January 23, 1986, another entry was placed on the

same reports indicating the "problem is considered closed."
141
Lawrence Mulloy and Lawrence Wear testified those

entries were "in error." They said:
Mr. Mulloy
: The problem assessment system was put in place to

provide visibility throughout the Shuttle system for the types of

problems that do occur, not just in flight, but also in qualification

tests, and in failure of hardware that is back for refurbishment at a

vendor or whatever. And it is a closed loop tracking system that

lists the anomaly .
Now, the entry that is shown in there that the

problem was closed prior to 51-L is in error. What happened there

was, one of your documents here which we did not discuss is the

letter from Mr. McDonald to Mr. Wear which proposed that this problem

be dropped from the problem assessment system and no longer be

tracked for the reasons stated in Mr. McDonald's letter.
That letter was in the review cycle. The

letter, I believe, was dated 10 December 1985. It came into the

center, it was in the review cycle. After Mr. Wear brought this

letter to my attention, my reaction was, we are not going to drop

this from the problem assessment system because the problem is not

resolved and it has to be dealt with on a flight-by-flight

basis.
Since that was going through the review cycle,

the people who run this problem assessment system erroneously entered

a closure for the problem on the basis of this submittal from

Thiokol. Having done that then for the 51-L review, this did not come

up in the Flight Readiness Review as an open launch constraint, so

you won't find a project signature because the PAS system showed the

problem was closed, and that was an error.
Chairman Rogers
: Who made the error? Do you know?
Mr. Mulloy

The people who do the problem assessment system.
Mr. Wear

Mr. Fletcher, and he reports within our quality organization at the

Flight Readiness Reviews, . . . as I think have been described to you

before. There is one from Thiokol to me, and there is one from my

group to Larry, and then Larry, of course, does one with the Shuttle

project office, and so forth, on up the line. At my review and at

Larry's review, here is a heads up given to the quality

representative at that board for what problems the system has open,

and they cross-check to make sure that we address that problem in the

readiness review.
On this particular occasion, there was no

heads up given because their Problem Assessment System considered

that action closed. That is unfortunate.
142
Project Manager Mulloy was asked during

Commission hearings about the original response to O-ring

erosion:
Mr. Hotz
: Mr. Mulloy, I would like to try to understand this in

somewhat simpler terms than you people are used to using.
Is it correct to state that when you

originally designed this joint and looked at it, that you did not

anticipate erosion of any of the O-ring during flights?
Mr. Mulloy

That is my understanding. I entered this program in November of 1982

and I wasn't there on the original design of the joint, but when I

took over the program there was no O-ring erosion anticipated.
Mr. Hotz
: So

that when you did run into signs of O-ring erosion, this was a bad

sign.
Mr. Mulloy

Yes, sir. .
Mr. Hotz
: So

then you decided to introduce a standard based on the measurement or

the possibility of the limits of O-ring erosion. And as those limits,

as the experience went up, your criteria for, say, flight went up

too.
In other words, when you experienced more than

maximum anticipated O-ring erosion, you waived the flight and said

"Well, it's possible to tolerate that. We still have a margin

left."
Mr. Mulloy

Are you speaking of the case where we did not have a primary

seal.
Mr. Hotz

Yes.
145
Mr. Mulloy
: Yes, sir.

That is correct. .
Mr. Hotz

Then you finally, you're talking about these margins of safety, and I

wonder if you could express in either percentages or actual

measurement terms-you have used the term "wide margin." I wonder if

you could give us a quantitative measurement as to what you consider

a wide margin?
Mr. Mulloy

Yes, sir. Well, as I said we had demonstrated that we could stand 125

thousandths of erosion and still seat. The maximum erosion that we

had seen in the case joint was on STS-2, which was 53 thousandths, so

that is a factor of two and a half .
Dr. Keel
: .

. . I think, Larry, if you go back and look at your Flight Readiness

Reviews, that you were relying on less margins than that.
You were arguing in the Flight Readiness

Reviews where you briefed the problems of primary O-ring erosion that

for the worst case for the field joint also that it would be 90

thousandths.
Mr. Mulloy

That is correct.
Dr. Keel
: At

that point you were pointing out that's okay, because you can seal at

95, not at 125 but at 95. It wasn't until later on during the process

that you determined you could seal at 125.
Mr. Mulloy

That is when we got the hot gas test data.
Dr. Keel
: So

that's a five percent margin, roughly, five and a half.
Mr. Mulloy

On the 90 to 95 on a max predictable, yes.
143
Temperature Effects
The record of the fateful series of NASA and

Thiokol meetings, telephone conferences, notes, and facsimile

transmissions on January 27th, the night before the launch of flight

51 -L, shows that only limited consideration was given to the past

history of O-ring damage in terms of temperature. The managers

compared as a function of temperature the flights for which thermal

distress of O-rings had been observed-not the frequency of occurrence

based on all flights (
Figure 6
). In such a comparison, there is nothing irregular in

the distribution of O-ring "distress" over the spectrum of joint

temperatures at launch between 53 degrees Fahrenheit and 75 degrees

Fahrenheit. When the entire history of flight experience is

considered, including"normal" flights with no erosion or blow-by, the

comparison is substantially different (
Figure 7
).
This comparison of flight history indicates

that only three incidents of O-ring thermal distress occurred out of

twenty flights with O-ring temperatures at 66 degrees Fahrenheit or

above, whereas, all four flights with O-ring temperatures at 63

degrees Fahrenheit or below experienced O-ring thermal

distress.
Consideration of the entire launch temperature

history indicates that the probability of O-ring distress is

increased to almost a certainty if the temperature of the joint is

less than 65.
Flight Readiness Reviews
It is clear that contractor and NASA program

personnel all believed that the O-ring erosion/blow-by anomaly, and

even the launch constraint, were problems that should be addressed in

NASA's Flight Readiness Review process. The Flight Readiness Review

is a multi-tiered review that is designed to create an information

flow from the contractor up through Level III at Marshall, then to

Level II officials from Johnson and Level I at Headquarters. With

regard to the Solid Rocket Booster, the process begins at the element

level and culminates in a coordinated Marshall position at the

subsequent Levels II and I Flight Readiness Review.
144
NASA policy manuals list four objectives of

the Shuttle Projects Flight Readiness Review, an intermediate review

between Level III and Level I, when contractors and Level III program

personnel consider the upcoming launch. The stated objectives

are:
"1.To provide the review team with

sufficient information necessary for them to make an independent

judgment regarding flight readiness.
"2. Review solved problems and previous flight

anomalies and establish confidence in solution rationale.
146
[top] Figure 6. Plot of flights with

incidents of O-ring thermal distress as function of

temperature.
[bottom] Figure 7. Plot of flights

with and without incidents of O-ring thermal distress. NOTE: Thermal

distress defined as O-ring erosion, blow-by, of excessive

heating.
147
] "3. Address all

problems, technical issues, open items and constraints requiring

resolution before flight.
"4. Establish the flight baseline

configuration particularly as it differs from previous missions."
145
The Commission has reviewed the various

documentary presentations made by Thiokol and NASA program people for

Flight Readiness Reviews on all Shuttle flights. The O-ring

presentations in those Flight Readiness Reviews have been summarized

in an Appendix to this report.
The erosion on STS-2 was not considered on any

level of the Flight Readiness Review for STS-3.
146
Similarly the heat effect on STS-6's primary O-ring in

the nozzle was not mentioned on the STS-7 Flight Readiness Review in

1983. However, the rationale for acceptance of the "secondary seal

condition" for the lightweight case first flown on STS-6 contained

the observation that an O-ring sealed during a Thiokol test under

3,000 psi where .125 inches had been cut out of the

O-ring.
147
The inattention to erosion and blow-by anomaly

changed when Thiokol filed a problem report on the field joint

erosion after STS 41-B. The O-ring problems (field and nozzle) on

41-B were briefed as a "technical issue" in the 41-C Flight Readiness

Review. "Probable causes" were defined as:
"Putty blow-through at ignition

causes cavity between putty and primary O-ring to fill during

pressurization. Inability of putty to withstand motor pressure. Air

entrapment in putty during mating. Blow holes in putty during joint

leak test."
Thiokol presented the question at its 41-C

preboard to Marshall, "If primary O-ring allowed a hot gas jet to

pass through, would the secondary O-ring survive impingement?"
148
At the 41 -C Level I Flight Readiness Review, on March

30, 1984, Marshall said the erosion phenomenon was "acceptable" and

that blow holes in the putty were the"most probable cause." The

rationale for the acceptance of the possibility of erosion on STS

41-C was:
"Conservative analysis indicates

max erosion possible:
".090 in. (field joint)
".090 in. (nozzle joint)
"Laboratory test of full scale O-ring/joint

cross section shows capability to sustain joint sealing integrity at

3,000 psi pressure using an O-ring with a simulated .095 in. erosion

depth.
"Recommendation:
"Fly STS 41-C accepting possibility of some

O-ring gas impingement."
149
The next significant treatment of the problem

occurred after the coldest flight, 51-C at 53 degrees in January

1985. In part, Thiokol's extensive analysis for the 51-E Flight

Readiness Review was due to the fact that four joints on 51-C had

problems.
150
Additionally, Mr. Mulloy's specific request for a

recap of the O-ring history undoubtedly prompted a full treatment.

Temperature was highlighted as a concern when Mulloy took Thiokol's

analysis up to the Shuttle Projects Office Flight Readiness Review.

That 18-page briefing concluded with the statement that: "STS 51-C

consistent with erosion data based. Low temperature enhanced

probability of blow-by. STS 51-C experienced worst case temperature

change in Florida history. STS 51-E could exhibit the same behavior.

Condition is acceptable."
151
At the Level I Flight Readiness Review for

51-E on February 21, 1985, the previous 18-page analysis had been

reduced to a one page chart with the resolution: "acceptable risk

because of limited exposure and redundancy (Ref. STS 41-C FRR)".
152
No mention of temperature was found in the Level I

report.
The last major discussion of erosion was at

the Level I Flight Readiness Review for STS 51-F (July 2,

1985).
153
An analysis of the failure of the nozzle primary

O-ring to seal due to erosion on flight STS 51-B (April 29, 1985) was

presented. This serious erosion was attributed to leak check

procedures. An increase in the nozzle leak check to 200 psi was

proposed to be a cure. There was no mention of the fact that .171

inches of erosion on the primary O-ring far exceeded a more recent

analysis model prediction of .070 inches maximum possible erosion.

This was a revision of the former prediction of .090 inches. The

launch constraint activated after STS 51-B was not specifically

listed in the Level I Flight Readiness Review for 51-F. The

Commission has also not found any mention of the duly 1985

constraint, or its waiver for subsequent Shuttle flights, in any

Flight Readiness Review briefing documents.
148
] The Commission's

review of the Marshall and Thiokol documentary presentations at the

various Flight Readiness Reviews revealed several significant trends.

First, O-ring erosion was not considered early in the program when it

first occurred. Second, when the problem grew worse after STS 41-B,

the initial analysis of the problem did not produce much research;

instead, there was an early acceptance of the phenomenon. Third,

because of a belief that in-flight O-ring erosion was "within the

data base" of prior experience, later Flight Readiness Reviews gave a

cursory review and often dismissed the recurring erosion as within

"acceptable" or "allowable" limits. Fourth, both Thiokol and Marshall

continued to rely on the redundancy of the secondary O-ring long

after NASA had officially declared that the seal was a non-redundant

single point failure. Finally, in 1985 when temperature became a

major concern after STS 51-C and when the launch constraint was

applied after 51-B, NASA Levels l and II were not informed of these

developments in the Flight Readiness Review process.
Findings
The genesis of the Challenger accident-the

failure of the joint of the right Solid Rocket Motor-began with

decisions made in the design of the joint and in the failure by both

Thiokol and NASA's Solid Rocket Booster project office to understand

and respond to facts obtained during testing.
The Commission has concluded that neither

Thiokol nor NASA responded adequately to internal warnings about the

faulty seal design. Furthermore, Thiokol and NASA did not make a

timely attempt to develop and verify a new seal after the initial

design was shown to be deficient. . Neither organization developed a

solution to the unexpected occurrences of O-ring erosion and blow-by

even though this problem was experienced frequently during the

Shuttle flight history. Instead, Thiokol and NASA management came to

accept erosion and blow-by as unavoidable and an acceptable flight

risk. Specifically, the Commission has found that:
1.The joint test and certification program was

inadequate. There was no requirement to configure the qualifications

test motor as it would be in flight, and the motors were static

tested in a horizontal position, not in the vertical flight

position.
2. Prior to the accident, neither NASA nor

Thiokol fully understood the mechanism by which the joint sealing

action took place.
3. NASA and Thiokol accepted escalating risk

apparently because they "got away with it last time." As Commissioner

Feynman observed, the decision making was:
"a kind of Russian roulette.

[The Shuttle] flies [with O-ring erosion] and

nothing happens. Then it is suggested, therefore, that the risk is no

longer so high for the next flights. We can lower our standards a

little bit because we got away with it last time.... You got away

with it but it shouldn't be done over and over again like that . "
154
4. NASA's system for tracking anomalies for

Flight Readiness Reviews failed in that, despite a history of

persistent O-ring erosion and blow-by, flight was still permitted. It

failed again in the strange sequence of six consecutive launch

constraint waivers prior to 51-L, permitting it to fly without any

record of a waiver, or even of an explicit constraint. Tracking and

continuing only anomalies that are "outside the data base" of prior

flight allowed major problems to be removed from, and lost by, the

reporting system.
5. The O-ring erosion history presented to

Level I at NASA Headquarters in August 1985 was sufficiently detailed

to require corrective action prior to the next flight.
6. A careful analysis of the flight history of

O-ring performance would have revealed the correlation of O-ring

damage and low temperature. Neither NASA nor Thiokol carried out such

an analysis; consequently, they were unprepared to properly evaluate

the risks of launching the 51-L mission in conditions more extreme

than they had encountered before.
149
References
1. Letter, Dorsey to

Hardy, November 7, 1978.
2. Report, "STS-3

through STS-25 Flight Readiness Reviews to Level III Center

Board," NASA.
3. Ibid.
4. Report, "Selection

of Contractor for Space Shuttle Program SRM," NASA. December 12,

1973; GAO Report B-17367, page 339.
5. Ibid., page

6.
6. Ibid., pages 21 and

22.
7. Ibid., page

18.
8. Ibid., page 7
9. Ibid., page

20
10. Chart, "SRM and

Titan III Clevis Joint Comparison," from Pelham presentation to

Commission Development and Production Subcommittees, March 17,

1986, page 3, PC 73978.
11. Chart,

"Segment/Segment Interface," from Pelham presentation to

Commission Development and Production Subcommittee, March 17,

1986, page 2, PC 73977
12. Report, Thiokol

Space Shuttle Joint Review`" Thiokol, February 25, 1986, PC

021453.
13. Ibid.
14. Ibid.
15. Report,

"Presidential Commission Development and Production Panel,

Response to Panel Question/Special Actions- SRM and Titan III

Clevis Joint Comparison," Thiokol, April 3, 1986, PC

073979.
16. Report, 'Original

Design of Joint Assembly SRB Motor Thiokol," Thiokol, July 13,

1973, PC 009350, and Commission Work Session, Panel on Development

and Production, April 17, 1986, page 18.
17. Report, "1974

Proposal Write Up On Case Design." Thiokol, 1974, page 4. 3-3, PC

010957.
18. Ibid page 4. 3-19,

PC 010973.
19. Commission Work

Session, Development and Production Panel, April 7, 1986, page

118.
20. Commission

Interview Transcript, McIntosh, H., April 2, 1986, page 5.
21. bid.
22. Letter, Brian

Russell to Bob Ebeling, Thiokol, April 9, 1986, PC 091702 and

Commission Hearing Transcript, May 2, 1986, pages

2653-2658.
23. Commission Hearing

Transcript, February 6, 1986, page 30.
24. Report, "Space

Shuttle Case Burst Test Report." Thiokol, December 21, 1977, PC

049551-049648, TWR-11664.
25. Ibid.
26. Report,

"Analytical Evaluation of the Space Shuttle Solid Rocket Motor

Tang/Clevis Joint Behavior," Thiokol, October 6, 1978, TWR-12019;

and Report, "SRM Clevis Joint Leakage Study," NASA, October 21.

1977.
27. Commission Hearing

Transcript, February 25, 1986, page 1435.
28. Commission Hearing

Transcript, May 2, 1986, page 2784.
29. Report, "SRM

Clevis Joint Leakage Study," NASA, October 21, 1977, PC

102337.
30. Letter, Miller to

Eudy, January 9, 1978, PC 009923.
31. Letter, Miller to

Eudy, January 19, 1979, PC 009921.
32. Ibid.
33. Ibid., footnote

31.
34. Commission Hearing

Transcript, May 2, 1986, page 2782.
35. Report, "Visit to

Precision Rubber Products Corporation and Parker Seal Company,"

NASA, February 6, 1979.
36. Ibid.
37. Commission Hearing

Transcript, May 2, 1986, page 2782.
38. Report, "Phase I

Design Certification Review," Thiokol, March 23, 1979,

TWR-12230.
39. Report,

"Analytical Evaluation of the Space Shuttle SRM Tang/Clevis Joint

Behavior," Thiokol. October 17, 1978. PC 102302.
40. Report, "Space

Shuttle Verification/Certification Review Propulsion Committee

Cognizant Engineers 5th Meeting,'' NASA, July 10, 1980, pages

C-7-22.
41. Commission Hearing

Transcript, May 2, 1986. page 2307
42. Report,

Verification/Certification Space Shuttle Program Response to

Assessment, " NASA, September 1980, page 59, PC 094010.
43. Report, "SRM

Program Response." NASA, August 15, 1980. PC 102359.
44. NASA Handbook,

NASA. 52300.4(1D-2). Appendix A, page a-1.
45. Commission

Interview Transcript, A. Aldrich, April 8, 1986, page 13.
46. Memorandum,

Abrahamson to Beggs, December 8, 1981.
47. Ibid.
48. Report. ''Erosion

of SRM Pressure Seals," Thiokol. August 19, 1985, Rev. A (February

10, 1986), page A- 4a.
49. Commission

Interview Transcript, Thomas J.W., April 10, 1986, pages 64-66:

and Reports, Marshall Space Flight Center Problem Assessment

Reports, NASA.
50 Report,

"Post-flight Evaluation of STS-2 SRM Components," Thiokol,

January. 1983, part 1, page 2, TWR 13286.
51. Report, "NASA

Response to Commission Request DP-006." NASA, March 17, 1986, PC

074021.
52. Report, "STS-8,

SRB Pre-Board Flight Readiness Review", Thiokol, July 29,

1983.
53. Report, "Retention

Rationale, SRM Simplex Seal," Thiokol, December 1, 1982, page 4.

and Report, 'Critical Items List." NASA, December 17, 1982.
54. Report. "SRB

Critical Items List," NASA, December 17, 1982.
55. Report, "Retention

Rationale, SRM Simplex Seal," Thiokol. December 1, 1982, page

5.
56. Ibid., page

4.
57. Commission

Interview Transcript, McIntosh. H., April 2, 1986, page 66.
58. Commission Hearing

Transcript, May 2, 1986, page 2729-30.
59. Ibid., footnote

31, page 1.
60. Commission Hearing

Transcript, February 26, 1986, pages 1700- 1701.
61. Commission Hearing

Transcript, February 26, 1986, pages 1514-1516.
62. Report, "Space

Transportation System Level I Change Request-Report, SRB Critical

Items List Requirements," NASA, March 2, 1983, page 1; and Report,

"Space Shuttle Program Requirements Control Board Directive -Level

II- SRB Critical Item List Requirements for SRM Case Joint

Assemblies." NASA, March 2, 1983, page 1.
63 Report, "Space

Shuttle Program Requirements Document Level I," NASA, June 30,

1977, page A-8.
64. Commission Hearing

Transcript, May 2, 1986. pages 2842 -2844.
65. Commission Hearing

Transcript, May 2. 1986, page 2845: and Report, "Space Shuttle

Program Requirements Control Board Directive-Level II, SRB

Critical Item List Requirements for SRM Case Joint Assemblies."

NASA, March 2, 1983, page 1.
66. Commission Hearing

Transcript, May 2, 1986, page 2852
67. Commission

Interview Transcript, A. Aldrich. and R. Kohrs, April 8, 1986,

pages 19-20.
68. Commission

Interview Transcript, L. Weeks, April 7, 1986. page 16.
69. Ibid., footnote

54.
150
70. Report, "MSFC Problem Assessment Report-

O-Ring Erosion in the Case to Nozzle Joint," February 26, 1986,

page 1 of 3; and Commission Interview Transcript, W. Hankins,

April 2, 1986, page 11.
71. Report, "Erosion

of SRM Pressure Seals," Thiokol, February 10, 1986, TWR-15150

Revision A; and Chart, "History of O-Ring Damage in Field Joints"

from Thiokol's presentation on February 25, 1986 to Commission, PC

072076 and PC072077.
72. Report, "Case and

Nozzle Joint Configuration Review," Thiokol, July 2, 1980, pages 2

and 5; and Report, "Erosion of SRM Pressure Seals," Thiolol,

August 19, 1986, pages A-4 and A-6, TWR-15150.
73. Report, "Char

Condition on O-Ring Seal in Forward Field Joint of SRM A57 of

STS-11 Flight Mission 41-B," Thiokol entry of March 12, 1984, page

5, TWR-14283; and Report, "MSFC Problem Assessment System-Segment

Joint Primary O-Ring Charred," NASA, February 17, 1984.
74. Report, "MSFC

Problem Assessment System-Segment Joint Primary O-Ring Charred,"

NASA, entry of March 12, 1984, page 5, TWR-14283.
75. Letter, Morefield

to Mulloy, March 9, 1984.
76. Report, "Flight

Readiness Review- 41C Level I," NASA, March 30, 1984.
77. Hans Mark 41-C

Programmatic Action Item, NASA, March 30, 1984.
78. Letter, Abrahamson

to Lucas, January 18, 1984, PC 008191.
79. Letter, Wear to

Kilminster, April 13, 1984, pages 1 and 2.
80. Report,

"Protection of Space Shuttle SRM Primary Motor Seals," Thiokol,

May 4, 1984, PC 014053.
81. Report, "Erosion

of SRM Pressure Seals Presentation to NASA HQ," Thiokol, August

19, 1985, page 1, and "STS 41-C Action Item Closeout," L. Mulloy,

S. Reinartz, NASA, February 20, 1986.
82. Routing slip,

Miller to Hardy, NASA, February 28, 1984, PC 0266494.
83. Report, "SRM FIeld

Joint Zinc Chromate Vacuum Putty Test Report," Thiokol, April 21,

1983, page 13.
84. Report, "SRM Joint

Putty, O-Ring, and Leak History," Thiokol, April 9, 1984, page 1,

TWR-13484.
85. Ibid.; and Report,

"Erosion of SRM Pressure Seals," Thiokol, TWR-15150, page D-16, PC

002963.
86. Ibid.; and Report,

"SRB SRS 9 Flight Readiness Review," NASA, November 4, 1983, page

35.
87. Report, "Erosion

of Solid Rocket Motor Pressure Seals," Thiokol, August 19, 1985,

TWR-15150, PC 021767.
88. Commission Hearing

Transcript, May 2, 1986, page 2687.
89. Commission Hearing

Transcript, May 2, 1986, page 2621.
90. Memorandum,

B.Russell, Thiokol, June 13, 1984, "Minutes of Telecon with NASA

MSFC on June 7, 1984," page 1, PC 102463.
91. Memorandum,

R.Russell, Thiokol, June 1, 1984, "Vacuum Putty/O-Ring Test

Results," page 1, PC 102460.
92. Memorandum,

J.Miller, March 6, 1985, NASA.
93. Memorandum, Young

to Director, Flight Crew Operations, March 3, 1986.
94. Commission

Interview Transcript, M. Silveira, April 16, 1986, page 30.
95. Commission

Interview Transcript, J.Beggs, May 1, 1986, pages 5-6.
96. Commission Hearing

Transcript, February 27, 1986, page 1899.
97. Report, "Flight

Readiness Review STS 51-E SRM-16," Thiokol, February 12, 1985,

pages 3-1 through 3-17.
98. Commission Hearing

Transcript, February 25, 1986, page 1392.
99. Commission Hearing

Transcript, Febrtuary 14, 1986, page 1202.
100. Report, "Problem

Assessment System Record #A07934," NASA, page 3, PC 037598.
101. Memorandum,

"51-C O-Ring Erosion Re: 51-E FRR," Mulloy to Wear, 03/31/85, PC

102482.
102. Report, "STS

51-E Flight Readiness Review," Thiokol, February 8, 1984,

TWR-14740 Rev. B Section 1, page 4.
103. Ibid., Section

6, page 4.
104. Report, "SRM

Seal Erosion Problems," NASA, March 19, 1986, PC 10235.
105. Report, "O-Ring

Resiliency Testing," Thiokol, June 3, 1985, PC 102509; and

Memorandum, "Actions Pertaining to Field Joint Secondary Seal,"

B.Russel, Thiokol, August 9, 1985, PC 102543.
106. Ibid.
107. Commission

Hearing Transcript, May 2, 1986, page 2591.
108. Commission

Hearing Transcript, May 2, 1986, pages 2606-2607.
109. Commission

Hearing Transcript, May 2, 1986, page 2591.
110. Memorandum,

Lindstrom to Distribution, NASA, September 15, 1980, page

1.
111. Report, "MSFC

Problem Assessment System," February 26, 1986, PC 037710.
112. Report, "SRM

Seal Erosion Problem, Revised," March 19, 1986, PC 037593.
113. Commission

Hearing Transcript, May 2, 1986, page 2735.
114. Letter, McDonald

to Wear, Thiokol, December 10, 1985, PC 49701.
115. Commission

Hearing Transcript, May 2, 1986, excerpt beginning pages 2590

through 2646.
116. Commission

Hearing Transcript, May 2, 1986, page 2589.
117. Commission

Hearing Transcript, May 2, 1986, page 2635.
118. Commission

Hearing Transcript, May 2, 1986, page 2867.
119. Memorandum,

Winterhaler to Weeks, June 28, 1985.
120. Memorandum, R.

Boisjoly, July 22, 1985.
121. Memorandum, R.

Boisjoly, July 31, 1985.
122. Letter, "Actions

Pertaining to SRM Field Joint Secondary Seal," Russell to Thomas,

August 9, 1985.
123. Report, "Erosion

of Solid Rocket Motor Pressure Seal Updated from August 19, 1985-

Revised February 10, 1986," Thiokol, TWR-15150, PC 000769.
124. Ibid.
125. Memorandum, Lund

to Sayer, August 20, 1985.
126. Memorandum, "SRM

Flight Seal Recommendation," Thompson to Stein, August 22,

1985.
127. Commission

Hearing Transcript, February 14, 1986, page 1220.
128. Report, "Program

Plan Improvement of Space Shuttle SRM Motor Seal," Thiokol, August

30, 1985, page 6.
129. Report, "Erosion

of SRM Pressure Seals," Thiokol, September 10, 1985, pages A-1 to

C-5.
130. Letter,

Kingsbury to Mulloy, September 5, 1985.
131. Report,

"Activity Report- Solid Rocket Motor Seal Problem Task Team

Status," Thiokol, October 4, 1985.
132. Memorandum,

Ebeling to McDonald, October 1, 1985, page 1.
133. Ibid., page 2;

and Report, "Erosion of SRM Pressure Seals, Update," February 10,

1986, pages A-4a, A-6a, TWR-1510, PC000760.
134. Report, "Level I

STS 61-C Flight Readiness Review," NASA, December 11, 1985.
135. Ibid., footnote

133; and Report, "Solid Motor Branch Significant Events," NASA,

December 12, 1985.
136. Commission

Hearing Transcript, May 2, 1986, pages 2746-2747.
137. Memorandum,

"Closure of SRM O-Ring Erosion Critical Problems," Russell to

McDonald, December 6, 1985.
138. Letter, McDonald

to Wear, December 10, 1985.
151
139. Commission Hearing Transcript, May 2,

1986, pages 2682-2695
140. Report, "Problem

Assessment System," NASA, entry dated December 18, 1985.
141. Ibid., entry

January 23, 1986.
142. Commission

Hearing Transcript, May 2, 1986. pages 2589-2590.
143. Ibid., pages

2619-2623.
144. Commission

Hearing Transcript, February 11, 1986, pages 65O-653.
145. Report, "Shuttle

Project Flight Readiness Review (Prelaunch Activities Team

Report)," NASA, December 29, 1983, page 75.
146. Reports, "STS-3

Flight Readiness Review for Levels I, II, III and

Contractor."
147. Commission

Hearing Transcript, February 26. 1986, page 1639.
148. Report, "STS-13

Solid (41-C) Rocket Motor Flight Readiness Review," Thiokol, March

2, 1984, page 2, TWR-14231.
149. Report STS 41-C

Flight Readiness Review Solid Rocket Booster," NASA, March 30,

1984, page 39.
150. Report, "O-Ring

Erosion on SRM-15," Thiokol, February 12, 1985, pages 1 through

17.
151. Report, "STS

51-E Flight Readiness Review," Thiokol, February 12, 1985,

TWR-14740 Rev. D., Section 3, page 17.
152. Report, "STS 51-E

Flight Readiness Review, Level 1," NASA, February 21, 1985, page

4.
153. Report, "STS 51-F

Flight Readiness Review, Level 1,'' NASA, July 2, 1985, page

5.
154. Commission

Hearing Transcript, April 3, 1986, page 2469.